NOTE - THE NOTED DISAPPROVED ITEMS MAY NOT CONSTITUTE A COMPLETE LIST OF VIOLATIONS. THE DESIGNER IS TO CONDUCT A COMPLETE RE-REVIEW OF THE PLANS FOR ADDITIONAL VIOLATIONS OF THE STANDARD COMMENTS AND INCORRECT INFORMATION PRIOR TO RESUBMITTING.

 System plans must be picked up within 30 days. All system plans left longer than 30 days will be discarded as abandoned.

SIGHTLINE MEDICAL CENTER - SUITE 100
01644 MEDICAL CENTER PT

Review DateStatusComment(s)
6/5/2013 FYI*****(STANDARD COMMENT) This project is: Sightline Medical Center, 1644 Medical Center Pt, Suite 100: interior remodel Date of Plans: 4.12.13 You can access our web site for the latest fire department plan review comments: 1. From www.pprbd.org, select PLAN REVIEW then FIND PLANS next COLORADO SPRINGS 2. Scroll down to the correct address. You may then select APPROVED/DISAPPROVED to view comments associated with that particular project.
FYI(STANDARD COMMENT) CHANGE OF USE/OCCUPANCY It appears this project is a change of use or occupancy for this building. As such, the building must meet the current adopted fire code for its new use/occupancy.
FYI(STANDARD COMMENT) IMPACT TO EXITING AND/OR FIRE PROTECTION SYSTEMS Egress components and fire protection systems that may be negatively impacted by yoru scope of work will be required to comply with the currently adopted fire code. As an example, if your work increases the occupant load of a space, the existing egress components will be required to comply with the requirements of the new occupant load.
Attention(STANDARD COMMENT) CONSTRUCTION SPLICES You are strongly encouraged to have any splices that may occur during this project, reviewed by CSFD. Failure to do so, can result in coordination issues that could prevent a final inspection from being completed, thus delaying the issuance of a Certificate of Occupancy.
FYI*****(STANDARD COMMENT) OCCUPANT LOAD THE OCCUPANT LOAD FOR THIS FACILITY IS: 66 The occupant load, calculated by the Regional Building Department shall be posted in a visible location. This determined number shall not be exceeded under any circumstance.
FYI(STANDARD COMMENT) EXIT SIGNS AND EMERGENCY LIGHTING: Exit Signs and Emergency Lighting shall be in compliance with the adopted building and fire code. Paths of egress will be verified to be compliant, even if they are beyond the scope of work. If your scope of work impacts the means of egress, i.e. a new conference room - the path of egress beyond that scope of work will be verified to make sure occupants can safely egress the building.
FYI(STANDARD COMMENT) LOCKING HARDWARE: All locking and latching devices shall comply with the requirements of the adopted building and fire code.
FYI*****(STANDARD COMMENT) HAZ-MAT CERTIFICATION FORM The hazardous materials amount certification form has been completed, submitted and attached to the building plans. This form states that there WILL NOT be excessive amounts of hazardous materials at this facility. CSFD Inspectors will verify this when the Fire final inspections of the occupancy are conducted.
FYI*****(STANDARD COMMENT) FIRE PROTECTION SYSTEMS The following systems are present or required in this facility: -XXX----Fire Alarm System --XXX---Water-Based Suppression System (fire sprinklers, standpipes, etc) Applicable Fire Protection System plans shall be submitted to the CSFD Construction Services office in the Regional Development Center.
FYI(STANDARD COMMENT 10) INSPECTIONS Due to the dynamic nature of inspectors schedules, PLEASE call your inspection requests in with ample time to allow scheduling. When calling, please have your complete CSFD plan review number(s) ready for each inspection request. ( i.e. 20001234 - HM -2 or 20000012 - CN - 1) The CSFD Approved sets of plans are to be on site for all inspections.
FYI(STANDARD COMMENT) JAH - SCHEDULING INSPECTIONS: Your assigned inspector is Jeff Hanenberg. Please call 719-385-5982 Extension 2 to schedule all construction related inspection activities.
FYI(STANDARD COMMENT) REVIEWS Colorado Springs Fire Department construction reviews are based upon information provided on the drawings and/or the attached reference material. Issues or features that are not presented within the construction documents are assumed to be complaint with applicable codes/standards. It is the responsibility of the building owner to ensure that minimum code requirements are met as established by the Authority Having Jurisdiction, whether or not the requirements are specifically indicated on the submitted construction documents. The CSFD has reviewed the submittal in accordance with the adopted fire code requirements, CSFD local amendments, City Code Standards, and applicable NFPA Standards. All plan review comments are subject to final on-site field inspections, and testing by the CSFD. Review and approval by the CSFD shall not relieve the applicant of the responsibility of compliance with the International Fire Code. (105.4.4)
FYI(STANDARD COMMENT) PERMITS Insure all applicable permits are obtained from the Regional Building Department and the Colorado Springs Fire Department for the work that is being done at this site.
5/17/2013 FYI*****(STANDARD COMMENT) This project is: Sightline Medical Center, 1644 Medical Center Pt, Suite 100: interior remodel Date of Plans: 4.12.13 You can access our web site for the latest fire department plan review comments: 1. From www.pprbd.org, select PLAN REVIEW then FIND PLANS next COLORADO SPRINGS 2. Scroll down to the correct address. You may then select APPROVED/DISAPPROVED to view comments associated with that particular project.
Disapproved*****(STANDARD COMMENT 19) DISAPPROVED COMMENTS The following information and/or corrections are needed prior to completing a full plan review. Please respond, in writing on letterhead, to each of the following comments: 1. Lasers often use specialized gases that may be regulated - please detail quantity information.OUTSTANDING FROM PREVIOUS REVIEW 2. Please provide an approximate inventory of any radiologocal pharmceuticals. OUTSTANDING FROM PREVIOUS REVIEW 3. Will there be any medical gases in this scope of work? If so, you must declare these gases, any piping systems and quantities. OUTSTANDING FROM PREVIOUS REVIEW 4. Plans and code study do not coordinate on the fire alarm system - the plans state one is required, the code study say it is not required, but then lists a manual system. Please clarify OUTSTANDING FROM PREVIOUS REVIEW Also review the disapproved plans for additional written comments prior to submittal of new plans.
Disapproved(STANDARD COMMENT) HAZARDOUS MATERIALS: Provide an inventory list, including their uses and amounts, for all chemicals and/or compressed gases, stored, handled and/or dispensed on site. Provide listed information on the TRIAGE form for all Use/Dispensing/Storage of Hazardous Materials and Flammable Liquids that will be used within this facility. PLEASE INSURE YOU ANSWER ALL QUESTIONS AT THE BOTTOM OF THE FORMS, AND FILL OUT THE REQUESTED INFORMATION. All forms and packets are available at https://www.springsgov.com/Page.aspx?NavID=1094.
FYI(STANDARD COMMENT) CORRECTIONS All corrections and comments are to be submitted back to CSFD in writing, or provid submittal sheets/drawings, etc as requested, to complete the review. Corrections are not accepted over the phone, via fax or verbally.
Attention(STANDARD COMMENT) THE DISAPPROVED ITEMS MAY NOT CONSITITUE A COMPLETE LIST OF VIOLATIONS. IT IS THE RESPONSIBILITY OF THE DESIGNER/ARCHITECT TO CONDUCT A COMPLETE RE-REVIEW OF THE PLANS FOR ADDITIONAL VIOLATIONS OF THE ADOPTED CODES/STANDARDS AND INCORRECT INFORMATION PRIO TO RESUBMITTING.
FYI*****(STANDARD COMMENT) DISAPPROVED ITEMS ADDRESSED The plans have been resubmitted and all the disapproved comments have been addressed and/or corrected as follows: 5. Additional exit signs are requried at changes of direction in the corridors - please correct the reflected ceiling plans accordingly. ADDITIONAL EXIT SIGNS ARE SHOWN.
FYI(STANDARD COMMENT) RESUBMITTALS Re-reviews may be submitted back to the CSFD by direct submittal at the Construction Services counter, or through the Regional Building Department's routing system.
FYI(STANDARD COMMENT) REVIEWS Colorado Springs Fire Department construction reviews are based upon information provided on the drawings and/or the attached reference material. Issues or features that are not presented within the construction documents are assumed to be complaint with applicable codes/standards. It is the responsibility of the building owner to ensure that minimum code requirements are met as established by the Authority Having Jurisdiction, whether or not the requirements are specifically indicated on the submitted construction documents. The CSFD has reviewed the submittal in accordance with the adopted fire code requirements, CSFD local amendments, City Code Standards, and applicable NFPA Standards. All plan review comments are subject to final on-site field inspections, and testing by the CSFD. Review and approval by the CSFD shall not relieve the applicant of the responsibility of compliance with the International Fire Code. (105.4.4)
4/26/2013 FYI*****(STANDARD COMMENT) This project is: Sightline Medical Center, 1644 Medical Center Pt, Suite XXX: interior remodel Date of Plans: 4.12.13 You can access our web site for the latest fire department plan review comments: 1. From www.pprbd.org, select PLAN REVIEW then FIND PLANS next COLORADO SPRINGS 2. Scroll down to the correct address. You may then select APPROVED/DISAPPROVED to view comments associated with that particular project.
Disapproved*****(STANDARD COMMENT 19) DISAPPROVED COMMENTS The following information and/or corrections are needed prior to completing a full plan review. Please respond, in writing on letterhead, to each of the following comments: 1. Lasers often use specialized gases that may be regulated - please detail quantity information. 2. Please provide anapproximate inventory of any radiologocal pharmceuticals. 3. Will there be any medical gases in this scope of work? If so, you must declare these gases, any piping systems and quantities. 4. Plans and code study do not coordinate on the fire alarm system - the plans state one is required, the code study say it is not required, but then lists a manual system. Please clarify 5. Additional exit signs are requried at changes of direction in the corridors - please correct the reflected ceiling plans accordingly. Also review the disapproved plans for additional written comments prior to submittal of new plans.
Disapproved(STANDARD COMMENT) TEMPORARY ADDRESS A temporary address has been assigned to these plans. CSFD will not approve the construction plans until the Regional Building Department Enumerations Office has assigned a permanent address to this facility, and has approved the construction plans.
Disapproved(STANDARD COMMENT) MULTI-TENANT BUILDINGS It appears this building will or does incorporate more than one tenant. As such, Enumerations requires secondary addressing for all tenant spaces. Provide a floor plan for each level or affected level of the building, clearing indicating each separate unit. Be sure to include the street address(es) for this location on the plan.
Disapproved(STANDARD COMMENT) HAZARDOUS MATERIALS: Provide an inventory list, including their uses and amounts, for all chemicals and/or compressed gases, stored, handled and/or dispensed on site. Provide listed information on the haz-mat permit amount certification form for all Use/Dispensing/Storage of Hazardous Materials and Flammable Liquids that will be used within this facility. PLEASE INSURE YOU ANSWER ALL QUESTIONS AT THE BOTTOM OF THE FORMS, AND FILL OUT THE REQUESTED INFORMATION. All forms and packets are available at https://www.springsgov.com/Page.aspx?NavID=1094.
FYI(STANDARD COMMENT) CORRECTIONS All corrections and comments are to be submitted back to CSFD in writing, or provid submittal sheets/drawings, etc as requested, to complete the review. Corrections are not accepted over the phone, via fax or verbally.
Attention(STANDARD COMMENT) THE DISAPPROVED ITEMS MAY NOT CONSITITUE A COMPLETE LIST OF VIOLATIONS. IT IS THE RESPONSIBILITY OF THE DESIGNER/ARCHITECT TO CONDUCT A COMPLETE RE-REVIEW OF THE PLANS FOR ADDITIONAL VIOLATIONS OF THE ADOPTED CODES/STANDARDS AND INCORRECT INFORMATION PRIO TO RESUBMITTING.
FYI(STANDARD COMMENT) RESUBMITTALS Re-reviews may be submitted back to the CSFD by direct submittal at the Construction Services counter, or through the Regional Building Department's routing system.
FYI(STANDARD COMMENT) REVIEWS Colorado Springs Fire Department construction reviews are based upon information provided on the drawings and/or the attached reference material. Issues or features that are not presented within the construction documents are assumed to be complaint with applicable codes/standards. It is the responsibility of the building owner to ensure that minimum code requirements are met as established by the Authority Having Jurisdiction, whether or not the requirements are specifically indicated on the submitted construction documents. The CSFD has reviewed the submittal in accordance with the adopted fire code requirements, CSFD local amendments, City Code Standards, and applicable NFPA Standards. All plan review comments are subject to final on-site field inspections, and testing by the CSFD. Review and approval by the CSFD shall not relieve the applicant of the responsibility of compliance with the International Fire Code. (105.4.4)
FYI(STANDARD COMMENT) PERMITS Insure all applicable permits are obtained from the Regional Building Department and the Colorado Springs Fire Department for the work that is being done at this site.


 