Traffic Cams

 

Proby Parkway- Phase I

Project Description: This project will implement the City portion of the Phase I improvements recommended by the South Metro Accessibility Study. The City portion will design and construct a new expressway (Milton E. Proby Parkway) between Academy Blvd. and Powers Blvd. This new expressway will be located just south of Drennan Rd. between Academy Blvd. and Hancock Expwy., and then will combine with existing Drennan Rd. as it approaches Powers Blvd. The anticipated budget for the Phase I portion of Proby Parkway is $53.1 million in 2008 dollars. The project scope includes preliminary and final design, permitting, public information and outreach, right-of-way (ROW) acquisition, roadway construction and construction management.

The new roadway is named in honor of Milton E. Proby, a local civil rights leader who passed away in 2006. Reverend Proby was a pastor at St. John Baptist Church in Colorado Springs for 48 years. Click here to view the Corridor Development plan.

Funding: PPRTA funds for this project are programmed as show below:

Budget: $53.1 M (in 2008 dollars)

Estimated project schedule (Proby Parkway): Design of the Proby Parkway expressway improvements between Academy Blvd. and Powers Blvd. in 2005-2008; ROW acquisition in 2008-2009; and construction activities from 2010-2011.

Web Site: www.probyparkway.com

Project Phone: 268-7430

Project E-mail: probyparkway@urscorp.com

Project Managers: Andy Garton, City Engineering Division
Clyde Pikkaraine
, City RTA.