Austin Bluffs Interchange at Union Boulevard

Austin Bluffs and Union traffic cam

Austin Bluffs and Union Blvd. Animation

Summer Quarterly Update


Construction progress as of May 16, 2008

Project Description: Proposed improvements include construction of a grade-separated single point urban interchange. Austin Bluffs Parkway will pass over Union Boulevard on a bridge. Entrance and exit ramps will be provided from Austin Bluffs, intersecting with Union at a single signalized intersection. Union will be widened at the intersection to allow double left-turn lanes and right-turn lanes for traffic operations. Three through lanes in each direction will continue on Union.


Click on map for a larger pdf view of alternate routes
Total estimated project cost: $35.7 million
2005 = $7,511,000
2006 = $15,000,000
2007 = $12,993,000

Estimated project schedule:
Construction - January 2007 - November 2008

Status Details: CH2M Hill was selected as the final design/construction management consultant. The PPRTA Board approved the consultant contract for final design/construction services for the Austin Bluffs Interchange at Union Boulevard project at its May 2005 meeting. Neighborhood meetings were held on August 31, 2005 and September 1, 2005. A project open house was held with the public on October 4, 2005. A construction contract with Lawrence Construction was approved by the PPRTA board on December 13, 2006. Construction began in January 2007 and a kick-off open house was held on January 29, 2007.


For more detailed plans, visit Web Site: www.projects.ch2m.com/austinbluffs/

Project Hotline: 719-598-2605

Project Managers: Scott Asher, CH2M Hill
Robin Kidder, City Engineering
Clyde Pikkaraine, City RTA

Bill Rumler, Lawrence Construction Co.
Kiley Wideman, Lawrence Construction Co. (PRACO)