RSS | Advanced Search | Site Map | Text Size a- A+
City of Colorado Springs
We Create Community

NOTE - THE NOTED DISAPPROVED ITEMS MAY NOT CONSTITUTE A COMPLETE LIST OF VIOLATIONS. THE DESIGNER IS TO CONDUCT A COMPLETE RE-REVIEW OF THE PLANS FOR ADDITIONAL VIOLATIONS OF THE STANDARD COMMENTS AND INCORRECT INFORMATION PRIOR TO RESUBMITTING.

 System plans must be picked up within 30 days. All system plans left longer than 30 days will be discarded as abandoned.

 
   

Review DateStatusComment(s)
12/13/2013 FYI12/13/13 NO CRYOGENIC NITROGEN WILL BE STORED OR USED ON SITE PER CSHP email CSHP has decided NOT to have liquid nitrogen at our Roundhouse site. Thanks, Deb Doan -----Original Message----- From: Tom Martin [tmartin@yowarch.com] Sent: Friday, December 13, 2013 10:03 AM Mountain Standard Time To: Doan, Deb Cc: kyeager@springsgov.com Subject: RE: size of West Dewar for liquid nitro Hi Deb, I just spoke with Kay telling her you have decided not to have stored nitrogen on premises. She will approve the plans if you will reply to this e-mail stating explicitly that you "will not have stored nitrogen on the premises." thanks, tm Thomas Martin Project Architect YOW Architects, PC 115 South Weber Street Suite 200 Colorado Springs, CO 80903 Office 719-475-8133 tmartin@yowarch.com ________________________________________ From: Doan, Deb [mailto:ddoan@CSHP.NET] Sent: Thursday, December 12, 2013 5:04 PM To: Tom Martin Subject: FW: size of West Dewar for liquid nitro Hi Tom, See Harry's info below. IF we get static for 10 liters of liquid nitro, we can take it away from them and say (truthfully) that we don't use it there anymore. Will that work? Thanks lots, From: Bovard, Harry Sent: Thursday, December 12, 2013 4:00 PM To: Doan, Deb Subject: Re: size of West Dewar for liquid nitro 10 liters. We should remove it as they never request that it be filled. From: Doan, Deb Sent: Thursday, December 12, 2013 11:47 AM To: Bovard, Harry Subject: size of West Dewar for liquid nitro Can you help me to identify the size of the Dewar used at West. We're getting all sorts of grief from the fire dept because we'll have liquid nitro at Roundhouse. They want us to put in extra ventilation! Anyway, if you can look up the size of the unit, I can get them the info. This is holding up our ability to get a permit9 Thanks lots! Deb Doan Director, Facilities & Support Services Colorado Springs Health Partners, PC 719 538 2910
12/4/2013 FYI*****(STANDARD COMMENT) This project is: CSHP 600 S 21ST St Interior Remodel Date of Plans: 11/20/13 You can access our web site for the latest fire department plan review comments: 1. From www.pprbd.org, select PLAN REVIEW then FIND PLANS next COLORADO SPRINGS 2. Scroll down to the correct address. You may then select APPROVED/DISAPPROVED to view comments associated with that particular project.
FYI*****(STANDARD COMMENT) REVISION: Revision Sequence: Second Scope of Revision: Address code review disapproval comments Date of Revision: No new revision date, walked through 12/4/13 NOTE: UPON THIS REVIEW IT IS NOTED THAT SEVERAL PAGES HAVE BEEN REVISED AND CHANGED WITH NO REDLINES SUBMITTED.
Attention(STANDARD COMMENT) IMPACT TO EXITING AND/OR FIRE PROTECTION SYSTEMS Egress components and fire protection systems that may be negatively impacted by yoru scope of work will be required to comply with the currently adopted fire code. As an example, if your work increases the occupant load of a space, the existing egress components will be required to comply with the requirements of the new occupant load.
Attention(STANDARD COMMENT) CONSTRUCTION SPLICES You are strongly encouraged to have any splices that may occur during this project, reviewed by CSFD. Failure to do so, can result in coordination issues that could prevent a final inspection from being completed, thus delaying the issuance of a Certificate of Occupancy.
Attention(STANDARD COMMENT) FIRE EXTINGUISHERS PLAN REVIEWS DO NOT INCLUDE REVIEW OF TYPE, SIZE OR PLACEMENT OF FIRE EXTINGUISHERS. Fire extinguisher type, size and placement shall be in accordance with the requirements of the currently adopted International Fire Code and the current edition of NFPA 10. The general fire extinguisher requirement for commercial structures is met with a typical dry chemical fire extinguisher with a minimum of 2A10BC rating. If there are special hazards in this building there may be requirements for specific or different fire extinguishers and this should be discussed with the reviewer at Colorado Springs Fire Department. If the owner and/or occupant wishes to deviate from the fire extinguisher listed above, please contact your inspector and/or plan reviewer early in the project to avoid delays at the time of final.
FYI(STANDARD COMMENT) FIRE EXTINGUISHERS - A, B, E OCCUPANCIES WITH FIRE SPRINKLERS Fire Extinguishers are not required in Group A, B and E occupancies equipped throughout with QUICK RESPONSE fire sprinklers except in following locations: Commercial cooking equipment Flammable or combustible liquid usage, dispensing and storage Special Hazard areas such as laboratories, computer and generator rooms As specified in Table 906.1 of 2009 IFC.
FYI(STANDARD COMMENT) FIRE EXTINGUISHERS Fire Extinguishers shall be provided in accordance with Section 906 of the 2009 IFC. Install extinguishers in highly visible and accessible locations, never in a dead-end area, and always try to place them near an exit pathway or at an exit(s). Mount 4" off floor to a maximum of 5 ft. to the top of the fire ext. (HINT: About waist high is perfect.) "FIRE EXTINGUISHER" signs may need to be posted to properly identify where the units are located if they're not highly visible.
FYI(STANDARD COMMENT) SUITE NUMBERS Provide suite numbers as per the adopted fire code. In malls or shopping center suites-4" high w/ 1/2" stroke and visible at 50 feet, hotel rooms 2" high w/ 1/4" stroke, and office suites 2" high w/ 1/4" stroke. Suite numbers shall be provided on the rear doors of multi-tenant strip centers as well.
Attention******************ATTENTION!!!!! (STANDARD COMMENT) EXIT SIGNS AND EMERGENCY LIGHTING: Exit Signs and Emergency Lighting shall be in compliance with the adopted building and fire code. Paths of egress will be verified to be compliant, even if they are beyond the scope of work. If your scope of work impacts the means of egress, i.e. a new conference room - the path of egress beyond that scope of work will be verified to make sure occupants can safely egress the building. ATTENTION!!!! FIRST REVIEW CALLED OUT EMERGENCY LIGHTING NEEDED ON SECOND FLOOR. NO CORRECTIONS HAVE BEEN MADE TO DRAWINGS, BUT THESE WILL BE REQUIRED IN ORDER TO PASS FIRE FINAL INSPECTION!!!!!!
Attention*****************ATTENTION!!!!!!!!!!!!!!!!! (STANDARD COMMENT) LOCKING HARDWARE: All locking and latching devices shall comply with the requirements of the adopted building and fire code. PAGE CSHP 9 HAS SPECIFIC NOTES REGARDING DOOR HARDWARE ISSUES THAT MUST BE COMPLIED WITH TO PASS A FIRE FINAL INSPECTION.
Attention*********************ATTENTION!!!!!!!!!!!!!!! (STANDARD COMMENT) HAZ-MAT REVIEW REQUIRED It appears that hazardous materials may be located on site. Your plans have been forwarded to the HazMat reviewer. If hazardous materials exceed exempt amounts, you will also be required to submit a Hazardous Material Management Plan for annual permitting. Additional tank installation permits and plan reviews may also be required. Check with the CSFD for details. CONTRACTOR WOULD NOT LEAVE PLANS FOR CHECK-IN TO HAZMAT. HE STATES HE WILL HAND CARRY!
Attention(STANDARD COMMENT 10) INSPECTIONS Due to the dynamic nature of inspectors schedules, PLEASE call your inspection requests in with ample time to allow scheduling. Please call 719-385-5982 Extension 2 to schedule all construction related inspection activities. When calling, please have your complete CSFD plan review number(s) ready for each inspection request. ( i.e. 20001234 - HM -2 or 20000012 - CN - 1) The CSFD Approved sets of plans are to be on site for all inspections.
FYI(STANDARD COMMENT) REVIEWS Colorado Springs Fire Department construction reviews are based upon information provided on the drawings and/or the attached reference material. Issues or features that are not presented within the construction documents are assumed to be complaint with applicable codes/standards. It is the responsibility of the building owner to ensure that minimum code requirements are met as established by the Authority Having Jurisdiction, whether or not the requirements are specifically indicated on the submitted construction documents. The CSFD has reviewed the submittal in accordance with the adopted fire code requirements, CSFD local amendments, City Code Standards, and applicable NFPA Standards. All plan review comments are subject to final on-site field inspections, and testing by the CSFD. Review and approval by the CSFD shall not relieve the applicant of the responsibility of compliance with the International Fire Code. (105.4.4)
FYI(STANDARD COMMENT) PERMITS Insure all applicable permits are obtained from the Regional Building Department and the Colorado Springs Fire Department for the work that is being done at this site.
11/25/2013 FYI*****(STANDARD COMMENT) This project is: CSHP 600 S 21st St 100 Remodel Date of Plans: 11/20/13 You can access our web site for the latest fire department plan review comments: 1. From www.pprbd.org, select PLAN REVIEW then FIND PLANS next COLORADO SPRINGS 2. Scroll down to the correct address. You may then select APPROVED/DISAPPROVED to view comments associated with that particular project.
E-Mail(STANDARD COMMENT) MEDICAL OFFICE BUILDING: This facility has the potential of containing compressed medical gases. Due to this concern, the CSFD will require a Hazardous Materials Triage form be completed, and provided to the CSFD for filing.
Disapproved*****(STANDARD COMMENT 19) DISAPPROVED COMMENTS The following information and/or corrections are needed prior to completing a full plan review. Please respond, in writing on letterhead, to each of the following comments: 1. CSFD Hazardous Materials Triage form must be completed, signed, dated and submitted with plans. Also review the disapproved plans for additional written comments prior to submittal of new plans.
FYI(STANDARD COMMENT) CORRECTIONS All corrections and comments are to be submitted back to CSFD in writing, or provid submittal sheets/drawings, etc as requested, to complete the review. Corrections are not accepted over the phone, via fax or verbally.
Attention(STANDARD COMMENT) THE DISAPPROVED ITEMS MAY NOT CONSITITUE A COMPLETE LIST OF VIOLATIONS. IT IS THE RESPONSIBILITY OF THE DESIGNER/ARCHITECT TO CONDUCT A COMPLETE RE-REVIEW OF THE PLANS FOR ADDITIONAL VIOLATIONS OF THE ADOPTED CODES/STANDARDS AND INCORRECT INFORMATION PRIO TO RESUBMITTING.
FYI(STANDARD COMMENT) RESUBMITTALS Re-reviews may be submitted back to the CSFD by direct submittal at the Construction Services counter, or through the Regional Building Department's routing system.


 

Contact Us: Email Us - Call: 385-CITY (719-385-2489) - RSS - Privacy, Linking and ADA Policies - designed, developed by projecta.com

printer friendly version Printer friendly version