RSS | Advanced Search | Site Map | Text Size a- A+
City of Colorado Springs
We Create Community

NOTE - THE NOTED DISAPPROVED ITEMS MAY NOT CONSTITUTE A COMPLETE LIST OF VIOLATIONS. THE DESIGNER IS TO CONDUCT A COMPLETE RE-REVIEW OF THE PLANS FOR ADDITIONAL VIOLATIONS OF THE STANDARD COMMENTS AND INCORRECT INFORMATION PRIOR TO RESUBMITTING.

 System plans must be picked up within 30 days. All system plans left longer than 30 days will be discarded as abandoned.

JOHNSON ORTHODONTICS - MAIN
05850 TUTT CENTER PT

Review DateStatusComment(s)
9/17/2013 FYI*****(STANDARD COMMENT) This project is: Johnson Orthodontics, 5850 Tutt Center Pt: interior finish - adding 2nd floor within building envelope Date of Plans: 9.6.13 You can access our web site for the latest fire department plan review comments: 1. From www.pprbd.org, select PLAN REVIEW then FIND PLANS next COLORADO SPRINGS 2. Scroll down to the correct address. You may then select APPROVED/DISAPPROVED to view comments associated with that particular project.
Disapproved*****(STANDARD COMMENT 19) DISAPPROVED COMMENTS The following information and/or corrections are needed prior to completing a full plan review. Please respond, in writing on letterhead, to each of the following comments: 1. Provide details on what the new space is being used for. Will an elevator be required to meet accessibility requirements? Also review the disapproved plans for additional written comments prior to submittal of new plans.
FYI(STANDARD COMMENT) CORRECTIONS All corrections and comments are to be submitted back to CSFD in writing, or provid submittal sheets/drawings, etc as requested, to complete the review. Corrections are not accepted over the phone, via fax or verbally.
FYI(STANDARD COMMENT) RESUBMITTALS Re-reviews may be submitted back to the CSFD by direct submittal at the Construction Services counter, or through the Regional Building Department's routing system.
FYI(STANDARD COMMENT) REVIEWS Colorado Springs Fire Department construction reviews are based upon information provided on the drawings and/or the attached reference material. Issues or features that are not presented within the construction documents are assumed to be complaint with applicable codes/standards. It is the responsibility of the building owner to ensure that minimum code requirements are met as established by the Authority Having Jurisdiction, whether or not the requirements are specifically indicated on the submitted construction documents. The CSFD has reviewed the submittal in accordance with the adopted fire code requirements, CSFD local amendments, City Code Standards, and applicable NFPA Standards. All plan review comments are subject to final on-site field inspections, and testing by the CSFD. Review and approval by the CSFD shall not relieve the applicant of the responsibility of compliance with the International Fire Code. (105.4.4)


 

Contact Us: Email Us - Call: 385-CITY (719-385-2489) - RSS - Privacy, Linking and ADA Policies - designed, developed by projecta.com

printer friendly version Printer friendly version