ENCORE SHOE DEPT - UNIT 321
01710 BRIARGATE BL

Review DateStatusComment(s)
8/22/2013 FYI*****(STANDARD COMMENT) This project is: Encore Shoe Department, 1710 Briargate Bl Suite 321: interior remodel Date of Plans: 7.2.13 You can access our web site for the latest fire department plan review comments: 1. From www.pprbd.org, select PLAN REVIEW then FIND PLANS next COLORADO SPRINGS 2. Scroll down to the correct address. You may then select APPROVED/DISAPPROVED to view comments associated with that particular project.
FYI(STANDARD COMMENT) IMPACT TO EXITING AND/OR FIRE PROTECTION SYSTEMS Egress components and fire protection systems that may be negatively impacted by yoru scope of work will be required to comply with the currently adopted fire code. As an example, if your work increases the occupant load of a space, the existing egress components will be required to comply with the requirements of the new occupant load.
FYI(STANDARD COMMENT) SUITE NUMBERS Provide suite numbers as per the adopted fire code. In malls or shopping center suites-4" high w/ 1/2" stroke and visible at 50 feet, hotel rooms 2" high w/ 1/4" stroke, and office suites 2" high w/ 1/4" stroke. Suite numbers shall be provided on the rear doors of multi-tenant strip centers as well.
FYI(STANDARD COMMENT) HIGH PILED-NOT APPROVED This facility will not be permitted to stock over 12 feet, and proper "NO STACKING OVER 12' " signs must be posted throughout the warehouse/stock room as per CSFD requirements.
FYI*****(STANDARD COMMENT) FIRE PROTECTION SYSTEMS The following systems are present or required in this facility: --XXX---Fire Alarm System - NOTIFICATION SHALL BE EXTENDED THROUGHOUT TENANT SPACE --XXX---Water-Based Suppression System (fire sprinklers, standpipes, etc) Applicable Fire Protection System plans shall be submitted to the CSFD Construction Services office in the Regional Development Center.
FYI(STANDARD COMMENT 10) INSPECTIONS Due to the dynamic nature of inspectors schedules, PLEASE call your inspection requests in with ample time to allow scheduling. Please call 719-385-5982 Extension 2 to schedule all construction related inspection activities. When calling, please have your complete CSFD plan review number(s) ready for each inspection request. ( i.e. 20001234 - HM -2 or 20000012 - CN - 1) The CSFD Approved sets of plans are to be on site for all inspections.
FYI(STANDARD COMMENT) REVIEWS Colorado Springs Fire Department construction reviews are based upon information provided on the drawings and/or the attached reference material. Issues or features that are not presented within the construction documents are assumed to be complaint with applicable codes/standards. It is the responsibility of the building owner to ensure that minimum code requirements are met as established by the Authority Having Jurisdiction, whether or not the requirements are specifically indicated on the submitted construction documents. The CSFD has reviewed the submittal in accordance with the adopted fire code requirements, CSFD local amendments, City Code Standards, and applicable NFPA Standards. All plan review comments are subject to final on-site field inspections, and testing by the CSFD. Review and approval by the CSFD shall not relieve the applicant of the responsibility of compliance with the International Fire Code. (105.4.4)
FYI(STANDARD COMMENT) PERMITS Insure all applicable permits are obtained from the Regional Building Department and the Colorado Springs Fire Department for the work that is being done at this site.
7/18/2013 FYI*****(STANDARD COMMENT) This project is: Encore Shoe Department, 1710 Briargate Bl Suite XXXX: interior remodel Date of Plans: 7.2.13 You can access our web site for the latest fire department plan review comments: 1. From www.pprbd.org, select PLAN REVIEW then FIND PLANS next COLORADO SPRINGS 2. Scroll down to the correct address. You may then select APPROVED/DISAPPROVED to view comments associated with that particular project.
Disapproved*****(STANDARD COMMENT 19) DISAPPROVED COMMENTS The following information and/or corrections are needed prior to completing a full plan review. Please respond, in writing on letterhead, to each of the following comments: 1. How high will merchandise be stored in the stock room? If over 12-feet, it is considered high pile storage and a separate review/permit will be required. See additional comment. 2. Exit signs shall be provided every 100-feet or the listed viewing distance, which ever is less. It is more than 100-feet from the existing signs provided at the store entries to the back wall - additional exit signage is needed. 3. Enumeration must approve the plans prior to CSFD - see additional comment. Also review the disapproved plans for additional written comments prior to submittal of new plans.
Disapproved(STANDARD COMMENT) TEMPORARY ADDRESS A temporary address has been assigned to these plans. CSFD will not approve the construction plans until the Regional Building Department Enumerations Office has assigned a permanent address to this facility, and has approved the construction plans.
Disapproved(STANDARD COMMENT) HIGH PILE STORAGE Based upon a review of the construction plans, it has been determined that this facility is capable of storing high-pile stock. If you are NOT planning on storing ordinary combustibles over 12-feet (or over 6-ft for high-hazard combustibles) then the owners must complete the NO STACKING AGREEMENT and attach it to the construction plans prior to submitting the plans for a fire department re-review. However, if you ARE planning on storing combustibles over the allowable limits, you will need to attach the "CSFD High-Pile Questionnaire" to the plans. All forms and packets are available at http://www.springsgov.com/Page.aspx?NavID=1094
FYI(STANDARD COMMENT) CORRECTIONS All corrections and comments are to be submitted back to CSFD in writing, or provid submittal sheets/drawings, etc as requested, to complete the review. Corrections are not accepted over the phone, via fax or verbally.
Attention(STANDARD COMMENT) THE DISAPPROVED ITEMS MAY NOT CONSITITUE A COMPLETE LIST OF VIOLATIONS. IT IS THE RESPONSIBILITY OF THE DESIGNER/ARCHITECT TO CONDUCT A COMPLETE RE-REVIEW OF THE PLANS FOR ADDITIONAL VIOLATIONS OF THE ADOPTED CODES/STANDARDS AND INCORRECT INFORMATION PRIO TO RESUBMITTING.
FYI(STANDARD COMMENT) RESUBMITTALS Re-reviews may be submitted back to the CSFD by direct submittal at the Construction Services counter, or through the Regional Building Department's routing system.
FYI(STANDARD COMMENT) REVIEWS Colorado Springs Fire Department construction reviews are based upon information provided on the drawings and/or the attached reference material. Issues or features that are not presented within the construction documents are assumed to be complaint with applicable codes/standards. It is the responsibility of the building owner to ensure that minimum code requirements are met as established by the Authority Having Jurisdiction, whether or not the requirements are specifically indicated on the submitted construction documents. The CSFD has reviewed the submittal in accordance with the adopted fire code requirements, CSFD local amendments, City Code Standards, and applicable NFPA Standards. All plan review comments are subject to final on-site field inspections, and testing by the CSFD. Review and approval by the CSFD shall not relieve the applicant of the responsibility of compliance with the International Fire Code. (105.4.4)


 