NOTE - THE NOTED DISAPPROVED ITEMS MAY NOT CONSTITUTE A COMPLETE LIST OF VIOLATIONS. THE DESIGNER IS TO CONDUCT A COMPLETE RE-REVIEW OF THE PLANS FOR ADDITIONAL VIOLATIONS OF THE STANDARD COMMENTS AND INCORRECT INFORMATION PRIOR TO RESUBMITTING.

 System plans must be picked up within 30 days. All system plans left longer than 30 days will be discarded as abandoned.

SDS FINISHED WATER PUMP STATION AREA 80
00977 MARKSHEFFEL RD

Review DateStatusComment(s)
8/13/2013 FYI*****(STANDARD COMMENT) This project is: Southern Delivery System Water Treatment Plant, 977 N Marksheffel Rd: Finished Water Pump Station Area 80 Date of Plans: 7.31.13 You can access our web site for the latest fire department plan review comments: 1. From www.pprbd.org, select PLAN REVIEW then FIND PLANS next COLORADO SPRINGS 2. Scroll down to the correct address. You may then select APPROVED/DISAPPROVED to view comments associated with that particular project.
Attention*****(STANDARD COMMENT) RED-LINED COMMENTS The following RED-LINED items are to be corrected prior to final inspection: 1. Fire Department Connection shall be located on the Plan Northeast corner of the building.
FYI(STANDARD COMMENT) GATES Gates securing the fire apparatus access road shall comply with all of the following criteria: 1. The minimum gate width shall be 16 feet (4877 mm) or as wide as necessary to facilitate the required turning radius. 2. Gates shall be of the swinging, sliding, or specifically approved lift type. 3. Construction of gate shall be of materials that allow manual operation by one person. 4. Gate components shall be maintained in an operative condition at all times and replaced or repaired when defective. 5. Electric gates shall be equipped with a Knox electronic override switch for all inbound directions of travel and any outbound direction of travel where automatic opening of the gate when a vehicle is present does not occur. 6. Manual opening gates shall not be locked with a padlock, or chain and padlock, unless they are provided with a Knox# padlock in series with the padlock, or chain and padlock. 7. Locking device specifications shall be submitted for approval by the fire code official. 8. Electric gate operators, where provided, shall be listed in accordance with UL 325. 9. Gates intended for automatic operation shall be designed, constructed and installed to comply with the requirements of ASTM F2200. 10. Electronically operated gates must stay open a minimum of 30 seconds when the Knox electronic override switch is turned on/off and must remain in the open position when the switch is turned on and left on. 11. A Knox fire department decal shall be placed adjacent to the Knox electronic override switch unless other approved fire department marking is provided. (2009 IFC 506.1.1, D103.5)
FYI(STANDARD COMMENT) FIRE FLOW TESTING - NEW HYDRANTS: All actual hydrant flow tests shall be conducted prior to the start of construction or the arrival of combustible material on site. It is the responsibility of the owner or their designated representative to ensure an approved water supply is provided.
Attention(STANDARD COMMENT) FIRE EXTINGUISHERS PLAN REVIEWS DO NOT INCLUDE REVIEW OF TYPE, SIZE OR PLACEMENT OF FIRE EXTINGUISHERS. Fire extinguisher type, size and placement shall be in accordance with the requirements of the currently adopted International Fire Code and the current edition of NFPA 10. The general fire extinguisher requirement for commercial structures is met with a typical dry chemical fire extinguisher with a minimum of 2A10BC rating. If there are special hazards in this building there may be requirements for specific or different fire extinguishers and this should be discussed with the reviewer at Colorado Springs Fire Department. If the owner and/or occupant wishes to deviate from the fire extinguisher listed above, please contact your inspector and/or plan reviewer early in the project to avoid delays at the time of final.
FYI*****(STANDARD COMMENT) KNOX (TM) ENTRY FOR NEW BUILDINGS KNOX (TM) -XXX-----Box ---XXX---Switch ARE required at this location. It is recommended that all KNOX (TM) boxes be placed in a highly accessible location approximately 10 feet off of the ground, and usually placed near the front entrance to the building. KNOX (TM) Security Equipment is the only approved type, and must be ordered directly through the CSFD Division of the Fire Marshal at 2880 International Circle, Suite 200-7, or by calling (719) 385-5982. ***************ALLOW AT LEAST 4 WEEKS DELIVERY TIME ************************* YOUR FINAL WILL NOT BE APPROVED WITHOUT THE KNOX SECURITY EQUIPMENT INSTALLED! YOU MUST ALSO CONTACT OUR OFFICE AT LEAST 1 WEEK PRIOR TO YOUR REQUEST FOR FIRE FINALS TO ARRANGE FOR A CSFD FIRE INSPECTOR TO MEET YOU AT THE SITE TO INSTALL PROPER KEYS FOR THE BUILDING INTO THE KNOX SECURITY UNIT.
FYI(STANDARD COMMENT) EXIT SIGNS AND EMERGENCY LIGHTING: Exit Signs and Emergency Lighting shall be in compliance with the adopted building and fire code. Paths of egress will be verified to be compliant, even if they are beyond the scope of work. If your scope of work impacts the means of egress, i.e. a new conference room - the path of egress beyond that scope of work will be verified to make sure occupants can safely egress the building.
FYI(STANDARD COMMENT) HIGH PILED-NOT APPROVED This facility will not be permitted to stock over 12 feet, and proper "NO STACKING OVER 12' " signs must be posted throughout the warehouse/stock room as per CSFD requirements.
FYI*****(STANDARD COMMENT) FIRE PROTECTION SYSTEMS The following systems are present or required in this facility: --XXX---Fire Alarm System -XXX----Water-Based Suppression System (fire sprinklers, standpipes, etc) Applicable Fire Protection System plans shall be submitted to the CSFD Construction Services office in the Regional Development Center.
FYI INSPECTIONS
FYI(STANDARD COMMENT) REVIEWS Colorado Springs Fire Department construction reviews are based upon information provided on the drawings and/or the attached reference material. Issues or features that are not presented within the construction documents are assumed to be complaint with applicable codes/standards. It is the responsibility of the building owner to ensure that minimum code requirements are met as established by the Authority Having Jurisdiction, whether or not the requirements are specifically indicated on the submitted construction documents. The CSFD has reviewed the submittal in accordance with the adopted fire code requirements, CSFD local amendments, City Code Standards, and applicable NFPA Standards. All plan review comments are subject to final on-site field inspections, and testing by the CSFD. Review and approval by the CSFD shall not relieve the applicant of the responsibility of compliance with the International Fire Code. (105.4.4)
FYI(STANDARD COMMENT) PERMITS Insure all applicable permits are obtained from the Regional Building Department and the Colorado Springs Fire Department for the work that is being done at this site.
6/26/2013 FYI*****(STANDARD COMMENT) This project is: Southern Delivery System Water Treatment Plant, 977 N Marksheffel Rd: Finished Water Pump Station Area 80 Date of Plans: 5.29.13 You can access our web site for the latest fire department plan review comments: 1. From www.pprbd.org, select PLAN REVIEW then FIND PLANS next COLORADO SPRINGS 2. Scroll down to the correct address. You may then select APPROVED/DISAPPROVED to view comments associated with that particular project.
Disapproved(STANDARD COMMENT) DEVELOPMENT PLAN Attach copies of the "City Approved" development plan to each set of construction plans submitted to the Colorado Springs Fire Department for review.
Disapproved(STANDARD COMMENT) WATER PLANS The City APPROVED" fire hydrant and water main plans are to be ATTACHED to all sets of construction plans for CSFD plan reviews.
Disapproved(STANDARD COMMENT) HAZARDOUS MATERIALS: Provide an inventory list, including their uses and amounts, for all chemicals and/or compressed gases, stored, handled and/or dispensed on site. Provide listed information on the haz-mat permit amount certification form for all Use/Dispensing/Storage of Hazardous Materials and Flammable Liquids that will be used within this facility. PLEASE INSURE YOU ANSWER ALL QUESTIONS AT THE BOTTOM OF THE FORMS, AND FILL OUT THE REQUESTED INFORMATION. All forms and packets are available at http://www.springsgov.com/Page.aspx?NavID=1094.
Disapproved(STANDARD COMMENT) 'F' OCCUPANCIES Provide a detailed explanation of the products being manufactured, the process you use to fabricate your product, the products and components used to make the items that are manufactured. If there are hazardous materials used for this process, provide detailed information as is listed in our haz-mat HMMP requirements. What materials are stored within the structure, how they are stored, the heights the products are stored at, etc. The better the explanation, the easier it is for us to review and approve the plans.
FYI(STANDARD COMMENT) CORRECTIONS All corrections and comments are to be submitted back to CSFD in writing, or provid submittal sheets/drawings, etc as requested, to complete the review. Corrections are not accepted over the phone, via fax or verbally.
Attention(STANDARD COMMENT) THE DISAPPROVED ITEMS MAY NOT CONSITITUE A COMPLETE LIST OF VIOLATIONS. IT IS THE RESPONSIBILITY OF THE DESIGNER/ARCHITECT TO CONDUCT A COMPLETE RE-REVIEW OF THE PLANS FOR ADDITIONAL VIOLATIONS OF THE ADOPTED CODES/STANDARDS AND INCORRECT INFORMATION PRIO TO RESUBMITTING.
FYI(STANDARD COMMENT) RESUBMITTALS Re-reviews may be submitted back to the CSFD by direct submittal at the Construction Services counter, or through the Regional Building Department's routing system.
FYI(STANDARD COMMENT) REVIEWS Colorado Springs Fire Department construction reviews are based upon information provided on the drawings and/or the attached reference material. Issues or features that are not presented within the construction documents are assumed to be complaint with applicable codes/standards. It is the responsibility of the building owner to ensure that minimum code requirements are met as established by the Authority Having Jurisdiction, whether or not the requirements are specifically indicated on the submitted construction documents. The CSFD has reviewed the submittal in accordance with the adopted fire code requirements, CSFD local amendments, City Code Standards, and applicable NFPA Standards. All plan review comments are subject to final on-site field inspections, and testing by the CSFD. Review and approval by the CSFD shall not relieve the applicant of the responsibility of compliance with the International Fire Code. (105.4.4)


 

Contact Us: Email Us - Call: 385-CITY (719-385-2489) - RSS - Privacy, Linking and ADA Policies - designed, developed by projecta.com

printer friendly version Printer friendly version