NOTE - THE NOTED DISAPPROVED ITEMS MAY NOT CONSTITUTE A COMPLETE LIST OF VIOLATIONS. THE DESIGNER IS TO CONDUCT A COMPLETE RE-REVIEW OF THE PLANS FOR ADDITIONAL VIOLATIONS OF THE STANDARD COMMENTS AND INCORRECT INFORMATION PRIOR TO RESUBMITTING.

 System plans must be picked up within 30 days. All system plans left longer than 30 days will be discarded as abandoned.

TNR DEVELOPMENT
02575 WESTON RD

Review DateStatusComment(s)
5/20/2013 FYI*****(STANDARD COMMENT) This project is: TNR Development, 2575 Weston Rd: interior remodel - change of occupancy from storage to manufacturing Date of Plans: 3.28.13 You can access our web site for the latest fire department plan review comments: 1. From www.pprbd.org, select PLAN REVIEW then FIND PLANS next COLORADO SPRINGS 2. Scroll down to the correct address. You may then select APPROVED/DISAPPROVED to view comments associated with that particular project.
FYI(STANDARD COMMENT) CHANGE OF USE/OCCUPANCY It appears this project is a change of use or occupancy for this building. As such, the building must meet the current adopted fire code for its new use/occupancy.
FYI(STANDARD COMMENT) IMPACT TO EXITING AND/OR FIRE PROTECTION SYSTEMS Egress components and fire protection systems that may be negatively impacted by yoru scope of work will be required to comply with the currently adopted fire code. As an example, if your work increases the occupant load of a space, the existing egress components will be required to comply with the requirements of the new occupant load.
Attention(STANDARD COMMENT) CONSTRUCTION SPLICES You are strongly encouraged to have any splices that may occur during this project, reviewed by CSFD. Failure to do so, can result in coordination issues that could prevent a final inspection from being completed, thus delaying the issuance of a Certificate of Occupancy.
FYI(STANDARD COMMENT) INTERIOR FINISH: Interior finish, to include wall coverings and window treatments shall comply with Table 803.3 of the 2009 IFC.
FYI(STANDARD COMMENT) EXTENSION CORDS AND MULTI-PLUG ADAPTERS Power sources shall comply with Section 605 of the 2009 IFC, especially with regard to the use of extension cords and multi-plug adapters.
Attention(STANDARD COMMENT) INFUSED PRODUCTS Infused product processes involve some chemicals, equipment, and procedures that must be reviewed and inspected by CSFD Hazardous Materials personnel. Please be informed that this will be required at any time the business is in operation upon discovery. Some examples to keep in mind are butane, isopropanol, high pressure Carbon Dioxide and or Carbon Dioxide generators/burners/cylinders, hydrogen peroxide, sulfur evaporators. These are not a conclusive list, just some common items found. Please notify CSFD plan reviewer and/or inspector immediately of any infusing process occuring on this site.
Attention(STANDARD COMMENT) FIRE EXTINGUISHERS PLAN REVIEWS DO NOT INCLUDE REVIEW OF TYPE, SIZE OR PLACEMENT OF FIRE EXTINGUISHERS. Fire extinguisher type, size and placement shall be in accordance with the requirements of the currently adopted International Fire Code and the current edition of NFPA 10. The general fire extinguisher requirement for commercial structures is met with a typical dry chemical fire extinguisher with a minimum of 2A10BC rating. If there are special hazards in this building there may be requirements for specific or different fire extinguishers and this should be discussed with the reviewer at Colorado Springs Fire Department. If the owner and/or occupant wishes to deviate from the fire extinguisher listed above, please contact your inspector and/or plan reviewer early in the project to avoid delays at the time of final.
FYI(STANDARD COMMENT) ADDRESSING Address shall be posted on street addressed side of structure. Minimum 5" numbers with 1/2" stroke. Contrasting color to background. (2009 IFC 505.1)
FYI*****(STANDARD COMMENT) OCCUPANT LOAD THE OCCUPANT LOAD FOR THIS FACILITY IS: 41 The occupant load, calculated by the Regional Building Department shall be posted in a visible location. This determined number shall not be exceeded under any circumstance.
FYI(STANDARD COMMENT) EXIT SIGNS AND EMERGENCY LIGHTING: Exit Signs and Emergency Lighting shall be in compliance with the adopted building and fire code. Paths of egress will be verified to be compliant, even if they are beyond the scope of work. If your scope of work impacts the means of egress, i.e. a new conference room - the path of egress beyond that scope of work will be verified to make sure occupants can safely egress the building.
FYI(STANDARD COMMENT) LOCKING HARDWARE: All locking and latching devices shall comply with the requirements of the adopted building and fire code.
FYI(STANDARD COMMENT) HAZ-MAT REVIEW REQUIRED It appears that hazardous materials may be located on site. Your plans have been forwarded to the HazMat reviewer. If hazardous materials exceed exempt amounts, you will also be required to submit a Hazardous Material Management Plan for annual permitting. Additional tank installation permits and plan reviews may also be required. Check with the CSFD for details.
FYI(STANDARD COMMENT 10) INSPECTIONS Due to the dynamic nature of inspectors schedules, PLEASE call your inspection requests in with ample time to allow scheduling. When calling, please have your complete CSFD plan review number(s) ready for each inspection request. ( i.e. 20001234 - HM -2 or 20000012 - CN - 1) The CSFD Approved sets of plans are to be on site for all inspections.
FYI(STANDARD COMMENT) JAH - SCHEDULING INSPECTIONS: Your assigned inspector is Jeff Hanenberg. Please call 719-385-5982 Extension 2 to schedule all construction related inspection activities.
FYI(STANDARD COMMENT) REVIEWS Colorado Springs Fire Department construction reviews are based upon information provided on the drawings and/or the attached reference material. Issues or features that are not presented within the construction documents are assumed to be complaint with applicable codes/standards. It is the responsibility of the building owner to ensure that minimum code requirements are met as established by the Authority Having Jurisdiction, whether or not the requirements are specifically indicated on the submitted construction documents. The CSFD has reviewed the submittal in accordance with the adopted fire code requirements, CSFD local amendments, City Code Standards, and applicable NFPA Standards. All plan review comments are subject to final on-site field inspections, and testing by the CSFD. Review and approval by the CSFD shall not relieve the applicant of the responsibility of compliance with the International Fire Code. (105.4.4)
FYI(STANDARD COMMENT) PERMITS Insure all applicable permits are obtained from the Regional Building Department and the Colorado Springs Fire Department for the work that is being done at this site.
4/17/2013 FYI*****(STANDARD COMMENT) This project is: TNR Development, 2575 Weston Rd: interior remodel - change of occupancy from storage to manufacturing Date of Plans: 3.28.13 You can access our web site for the latest fire department plan review comments: 1. From www.pprbd.org, select PLAN REVIEW then FIND PLANS next COLORADO SPRINGS 2. Scroll down to the correct address. You may then select APPROVED/DISAPPROVED to view comments associated with that particular project.
Disapproved*****(STANDARD COMMENT 19) DISAPPROVED COMMENTS The following information and/or corrections are needed prior to completing a full plan review. Please respond, in writing on letterhead, to each of the following comments: 1. Incorrect hazmat form was provided - please fill out the HazMat Triage form (provided) and any additional information requested by the form. See additional Comment 2. This project appears to be capable of high pile storage - see additional comment. Also review the disapproved plans for additional written comments prior to submittal of new plans.
Disapproved(STANDARD COMMENT) HIGH PILE STORAGE Based upon a review of the construction plans, it has been determined that this facility is capable of storing high-pile stock. If you are NOT planning on storing ordinary combustibles over 12-feet (or over 6-ft for high-hazard combustibles) then the owners must complete the NO STACKING AGREEMENT and attach it to the construction plans prior to submitting the plans for a fire department re-review. However, if you ARE planning on storing combustibles over the allowable limits, you will need to attach the "CSFD High-Pile Questionnaire" to the plans. All forms and packets are available at http://www.springsgov.com/Page.aspx?NavID=1094
Disapproved(STANDARD COMMENT) HAZARDOUS MATERIALS: Provide an inventory list, including their uses and amounts, for all chemicals and/or compressed gases, stored, handled and/or dispensed on site. Provide listed information on the haz-mat permit amount certification form for all Use/Dispensing/Storage of Hazardous Materials and Flammable Liquids that will be used within this facility. PLEASE INSURE YOU ANSWER ALL QUESTIONS AT THE BOTTOM OF THE FORMS, AND FILL OUT THE REQUESTED INFORMATION. All forms and packets are available at http://www.springsgov.com/Page.aspx?NavID=1094.
FYI(STANDARD COMMENT) CORRECTIONS All corrections and comments are to be submitted back to CSFD in writing, or provid submittal sheets/drawings, etc as requested, to complete the review. Corrections are not accepted over the phone, via fax or verbally.
Attention(STANDARD COMMENT) THE DISAPPROVED ITEMS MAY NOT CONSITITUE A COMPLETE LIST OF VIOLATIONS. IT IS THE RESPONSIBILITY OF THE DESIGNER/ARCHITECT TO CONDUCT A COMPLETE RE-REVIEW OF THE PLANS FOR ADDITIONAL VIOLATIONS OF THE ADOPTED CODES/STANDARDS AND INCORRECT INFORMATION PRIO TO RESUBMITTING.
FYI(STANDARD COMMENT) RESUBMITTALS Re-reviews may be submitted back to the CSFD by direct submittal at the Construction Services counter, or through the Regional Building Department's routing system.
FYI(STANDARD COMMENT) REVIEWS Colorado Springs Fire Department construction reviews are based upon information provided on the drawings and/or the attached reference material. Issues or features that are not presented within the construction documents are assumed to be complaint with applicable codes/standards. It is the responsibility of the building owner to ensure that minimum code requirements are met as established by the Authority Having Jurisdiction, whether or not the requirements are specifically indicated on the submitted construction documents. The CSFD has reviewed the submittal in accordance with the adopted fire code requirements, CSFD local amendments, City Code Standards, and applicable NFPA Standards. All plan review comments are subject to final on-site field inspections, and testing by the CSFD. Review and approval by the CSFD shall not relieve the applicant of the responsibility of compliance with the International Fire Code. (105.4.4)


 