RSS | Advanced Search | Site Map | Text Size a- A+
City of Colorado Springs
We Create Community

NOTE - THE NOTED DISAPPROVED ITEMS MAY NOT CONSTITUTE A COMPLETE LIST OF VIOLATIONS. THE DESIGNER IS TO CONDUCT A COMPLETE RE-REVIEW OF THE PLANS FOR ADDITIONAL VIOLATIONS OF THE STANDARD COMMENTS AND INCORRECT INFORMATION PRIOR TO RESUBMITTING.

 System plans must be picked up within 30 days. All system plans left longer than 30 days will be discarded as abandoned.

KUM AND GO #676 - MAIN
02588 AIRPORT RD

Review DateStatusComment(s)
2/12/2014 ApprovedCopies submitted for signature and CSFD file
1/8/2014 FYI*****(STANDARD COMMENT 1) This project is: Kum and Go 2588 Airport Rd New Convenience Store You can access our web site for the latest fire department plan review comments: 1. From www.pprbd.org, select PLAN REVIEW then FIND PLANS next COLORADO SPRINGS 2. Scroll down to the correct address. You may then select APPROVED/DISAPPROVED to view comments associated with that particular project.
Attention*****(STANDARD COMMENT 2) BUILDING DATA: Size of Bldg. ---4992-- sq ft Construction Type ---VB--- Fire Sprinklers Y----- N--XX--- Fire Walls Y ----- Rating ----- N --XX-- Required GPM: ---2000-- gpm # of hydrant(s) required: --2--- Max AVG spacing between hydrants: ---450-- ft Max hose lay: --225--- ft
FYI*****(STANDARD COMMENT) SCOPE OF WORK: -----MAIN EXTENSION -----UTILITY SERVICE PLAN -----DOMESTIC ONLY - NO FIRE INSPECTION REQUIRED -----FIRE/DOMESTIC - --XX---WATER PLAN ---XX--Site Specific -----Subdivision - No Fire Inspection Required
FYI*****(STANDARD COMMENT) FIRE FLOW/HYDRANT REQUIREMENTS MET: On this site the theoretical water flows are --3400-- gpm, and the numbers of hydrant(s) are --2--. This site, based upon the provided theoretical modeled fire flows, appear to meet the minimum flow requirements and/or the number of hydrant(s) for this structure.
FYI*****(STANDARD COMMENT) REVISION: Revision Sequence: Second Scope of Revision: Address proximity to existing hydrant and ownership of hydrant Date of Revision: 01/10/14
Attention(STANDARD COMMENT) READY FOR SIGNATURES: The water plans appear ready for signature as long as all disapproved comments have been addressed. Please provide one hard copy for CSFD records along with your final copies for our signature.
FYI(STANDARD COMMENT 10) INSPECTIONS Please call 719-385-5982 Extension 2 to schedule all construction related inspection activities. You will need to schedule an inspection at the time of Framing and a final inspection near completion. Due to the dynamic nature of inspectors schedules, PLEASE call your inspection requests in with ample time to allow scheduling. When calling, please have your complete CSFD plan review number(s) ready for each inspection request. ( i.e. 2013-1234 - HS-1) The CSFD Approved sets of plans are to be on site for all inspections.
FYI(STANDARD COMMENT) DISAPPROVED ITEMS ADDRESSED: The plans have been resubmitted and all the disapproved comments have been addressed and/or corrected as follows: 1. Proposed hydrant is being relocated from existing location (not added). 2. Legal papers submitted stating ownership of existing hydrant follows land ownership. New convenience store has purchased Lot 2 and so existing hydrant will also be property of Lot 2. Paperwork to file.
FYI(STANDARD COMMENT) REVIEWS: Colorado Springs Fire Department construction reviews are based upon information provided on the drawings and/or the attached reference material. Issues or features that are not presented within the construction documents are assumed to be complaint with applicable codes/standards. It is the responsibility of the building owner to ensure that minimum code requirement are met as established by the Authority Having Jurisdiction, whether of not the requirements are specifically indicated on the submitted construction documents. The CSFD has reviewed the submittal in accordance with the fire code requirements of the 2009 International Fire Code, CSFD local amendments, City Code Standards, and applicable NFPA Standards. All plan review comments are subject to final on-site field inspections, and testing by the CSFD. Review and approval by the CSFD shall not relieve the applicant of the responsibility of compliance with the International Fire Code. (105.4.4)
1/3/2014 FYI*****(STANDARD COMMENT 1) This project is: Kum and Go Store 676, 2588 Airport Rd: You can access our web site for the latest fire department plan review comments: 1. From www.pprbd.org, select PLAN REVIEW then FIND PLANS next COLORADO SPRINGS 2. Scroll down to the correct address. You may then select APPROVED/DISAPPROVED to view comments associated with that particular project.
Attention*****(STANDARD COMMENT 2) BUILDING DATA: Size of Bldg. --4992--- sq ft Construction Type --V-B---- Fire Sprinklers Y----- N--XXX--- Fire Walls Y ----- Rating ----- N --XXX--- Required GPM: --2000--- gpm # of hydrant(s) required: --2--- Max AVG spacing between hydrants: --450--- ft Max hose lay: --225--- ft
FYI*****(STANDARD COMMENT) SCOPE OF WORK: TBD
FYI*****(STANDARD COMMENT) FIRE FLOW/HYDRANT REQUIREMENTS MET: On this site the theoretical water flows are -3400--- gpm, and the numbers of hydrant(s) are -2---. This site, based upon the provided theoretical modeled fire flows, appear to meet the minimum flow requirements and/or the number of hydrant(s) for this structure.
DisapprovedDISAPPROVED The following information and/or corrections are needed prior to completing a full plan review: 1. Plans propose to install a fire hydrant to the NW of the structure - please check for existing private hydrants as it appears there is one within 100-feet of the propsed hydrant. This would not be prudent design for this facility. A private hydrant use agreement may be needed. Also: 1) Review all redline comments and address each one. 2) Return ALL red lined plan sets for each re-review.
Disapproved(DISAPPROVED) PRIVATE FIRE HYDRANT USE AGREEMENT: PRIVATE FIRE HYDRANTS LOCATED IN THE CITY OF COLORADO SPRINGS ARE NOT TO BE USED BY ANYONE OTHER THAN THE OWNER(S) OF THE FIRE HYDRANT(S). It is for this reason that you must have city fire hydrants in the immediate vicinity, or, if there are private hydrants, you must have official permission from the owner(s) for you to use them for your new structure. Once you have spoken with the owners of the hydrant you must obtain a legal HYDRANT USE AGREEMENT between yourself and the owners of the hydrant(s). This is a legal document, and it must be registered through The County of El Paso as such. Once you have received your official paperwork back from The County, and it is correctly signed and sealed, the CSFD will grant approval for you to use the private hydrants as a part of the fire protection for your structure. For samples of a PRIVATE HYDRANT USE AGREEMENTS, please contact the CSFD Cosntruction Services.
FYI(STANDARD COMMENT) REVIEWS: Colorado Springs Fire Department construction reviews are based upon information provided on the drawings and/or the attached reference material. Issues or features that are not presented within the construction documents are assumed to be complaint with applicable codes/standards. It is the responsibility of the building owner to ensure that minimum code requirement are met as established by the Authority Having Jurisdiction, whether of not the requirements are specifically indicated on the submitted construction documents. The CSFD has reviewed the submittal in accordance with the fire code requirements of the 2009 International Fire Code, CSFD local amendments, City Code Standards, and applicable NFPA Standards. All plan review comments are subject to final on-site field inspections, and testing by the CSFD. Review and approval by the CSFD shall not relieve the applicant of the responsibility of compliance with the International Fire Code. (105.4.4)


 

Contact Us: Email Us - Call: 385-CITY (719-385-2489) - RSS - Privacy, Linking and ADA Policies - designed, developed by projecta.com

printer friendly version Printer friendly version