NOTE - THE NOTED DISAPPROVED ITEMS MAY NOT CONSTITUTE A COMPLETE LIST OF VIOLATIONS. THE DESIGNER IS TO CONDUCT A COMPLETE RE-REVIEW OF THE PLANS FOR ADDITIONAL VIOLATIONS OF THE STANDARD COMMENTS AND INCORRECT INFORMATION PRIOR TO RESUBMITTING. System plans must be picked up within 30 days. All system plans left longer than 30 days will be discarded as abandoned.
NEW DAWN ASSISTED LIVING BUILDING A 04145 BRIARGATE PY
| Review Date | Status | Comment(s) |
| 1/30/2013 |
Attention | INTEGRAL GENERATOR TANK WITH GENERATOR. 1/30/13 PHONE CALL FROM TERRY POLSON
PLANS SUBMITTED WITHOUT PERMIT APPLICATION FORMS AND SUPPORT DOCUMENTS RE TANK SPECS ETC.
PER TERRY, 1/30/13: NO HAZMAT ON THIS SITE. ONLY A GENERATOR WITH TANK.
PER YEAGER:
PLAN REVIEW FOR HAZMAT WILL BE N/A. YEAGER WILL SIGN PLANS N/A. RESUBMIT TANK/GENERATOR WITH PERMIT APPLICATION AND DOCUMENTS UNDER DEFERRED SUBMITTAL-SEPARATE COVER. NO HAZMAT REVIEW. WEBSITE FOR PERMIT FORMS AND CHECKLIST FOR ATTACHMENTS AND PLAN DOCUMENTS.
REDUCE SIZE SET OF PLANS FOR PERMIT APPLICATION.
THIS WILL NOT DELAY YOUR CONSTRUCTION PLANS OR PERMIT.
TERRY NOT SURE IF MORE THAN ONE GENERATOR AT THIS TIME.
1/30/13: PHONE CALL
PER TERRY ONE GENERATOR ONLY AT BUILDING C.
|
| FYI | New Dawn Assisted Living, The Medical Pavillion at Briargate,
FH:Required Flow: gpm /# Hydrants /On site flow:
DV: Amendment to the original developmetn plan to adjust the location of Building D and adjust location of fire lanes. This amendment affects three buildings; Located northwest of Family PLace and Austin Bluffs Parkway.
Additional Comments: |
|