NOTE - THE NOTED DISAPPROVED ITEMS MAY NOT CONSTITUTE A COMPLETE LIST OF VIOLATIONS. THE DESIGNER IS TO CONDUCT A COMPLETE RE-REVIEW OF THE PLANS FOR ADDITIONAL VIOLATIONS OF THE STANDARD COMMENTS AND INCORRECT INFORMATION PRIOR TO RESUBMITTING.

 System plans must be picked up within 30 days. All system plans left longer than 30 days will be discarded as abandoned.

RIDGEVIEW ANIMAL HOSPITAL
05886 TUTT BL

Review DateStatusComment(s)
8/5/2013 FYI*****(STANDARD COMMENT 1) This project is: Ridgeview Animal Hospital, 5886 Tutt Bl: new vetrinary facility - exterior storage medical gases You can access our web site for the latest fire department plan review comments: 1. From www.pprbd.org, select PLAN REVIEW then FIND PLANS next COLORADO SPRINGS 2. Scroll down to the correct address. You may then select APPROVED/DISAPPROVED to view comments associated with that particular project.
Attention*****(STANDARD COMMENT 2) BUILDING DATA: Size of Bldg. -12,000--- sq ft Construction Type ---v-b--- Fire Sprinklers Y----- N--xxx-- Fire Walls Y ----- N -xxx---- Required GPM: --3000--- gpm # of hydrant(s) required: --3--- Max AVG spacing between hydrants: --400--- ft Max hose lay: ---225-- ft
FYI(STANDARD COMMENT) FIRE FLOW TESTING: (STANDARD COMMENT) FIRE FLOW TESTING - NEW HYDRANTS: All actual hydrant flow tests shall be conducted prior to the start of construction or the arrival of combustible material on site. It is the responsibility of the owner or their designated representative to ensure an approved water supply is provided. (STANDARD COMMENT) WATER SUPPLY REQUIRED ON SITE Required water supplies for fire protection, either temporary or permanent, shall be made available as soon as combustible material arrives on the site. (2009 1412) ALL HYDRANT TESTS SHALL BE CONDUCTED BEFORE ON-SITE CONSTRUCTION IS STARTED!!! PUBLIC/CITY OWNED HYDRANTS: Contact SEAN HIGBEE, CSU at 668-4595 or via email at shigbee@csu.org to schedule an ACTUAL flow test. Be sure to provide them with a CSFD plan review number to include with their flow reports. CSFD need not be present when City Utilities flow tests hydrants as we will accept their reports. PLEASE ALLOW 1-2 WEEKS NOTICE PRIVATE HYDRANTS: Contact your assigned inspector below to schedule a flow test of PRIVATE OWNED hydrants. A contractor capable of performing the test will be required as CSFD Inspectors WITNESS only. CSFD will not accept flow tests we have not witnessed.
FYI(STANDARD COMMENT 8) GENERAL INSPECTIONS/PLANS & SCHEDULING Minimum notice of one week is required for all inspections. PLEASE plan ahead - call your inspections in with ample time to allow adequate scheduling. When calling, please have your complete CSFD plan review number(s) ready for each inspection request. ( For Example: 2005-1234- HS-2) The CSFD APPROVED sets of plans SHALL be on site for all inspections.
FYI(STANDARD COMMENT) REVIEWS: Colorado Springs Fire Department construction reviews are based upon information provided on the drawings and/or the attached reference material. Issues or features that are not presented within the construction documents are assumed to be complaint with applicable codes/standards. It is the responsibility of the building owner to ensure that minimum code requirement are met as established by the Authority Having Jurisdiction, whether of not the requirements are specifically indicated on the submitted construction documents. The CSFD has reviewed the submittal in accordance with the fire code requirements of the 2009 International Fire Code, CSFD local amendments, City Code Standards, and applicable NFPA Standards. All plan review comments are subject to final on-site field inspections, and testing by the CSFD. Review and approval by the CSFD shall not relieve the applicant of the responsibility of compliance with the International Fire Code. (105.4.4)
6/25/2013 FYI*****(STANDARD COMMENT 1) This project is: Ridgeview Animal Hospital, 5886 Tutt Bl: new veterinary facility Date of Plans: 6.7.13 You can access our web site for the latest fire department plan review comments: 1. From www.pprbd.org, select PLAN REVIEW then FIND PLANS next COLORADO SPRINGS 2. Scroll down to the correct address. You may then select APPROVED/DISAPPROVED to view comments associated with that particular project.
FYI*****(STANDARD COMMENT) SCOPE OF WORK: --xxx---WATER PLAN
Disapproved(DISAPPROVED) BUILDING DATA The "BUILDING DATA" information must be provided for each building, and should be indicated inside the footprint layout of the building, or just next to the footprint, and on each of your plan sheets that are to be signed by CSFD: Please refer to our Water Supplies Information packet for the required information/template.
Disapproved(DISAPPROVED) FIRE FLOW REPORT Provide confirmation on the fire flow results from Colorado Springs Utilities. A copy of their report for this area is required to be provided with your plan submittals. When multiple fire flows are provided from CSU, please indicate all flows on your submitted plans. NOTE - To request a fire flow report, please go to: https://www.csu.org/Pages/construction-drawing-review.aspx
FYI(STANDARD COMMENT) REVIEWS: Colorado Springs Fire Department construction reviews are based upon information provided on the drawings and/or the attached reference material. Issues or features that are not presented within the construction documents are assumed to be complaint with applicable codes/standards. It is the responsibility of the building owner to ensure that minimum code requirement are met as established by the Authority Having Jurisdiction, whether of not the requirements are specifically indicated on the submitted construction documents. The CSFD has reviewed the submittal in accordance with the fire code requirements of the 2003 International Fire Code, CSFD local amendments, City Code Standards, and applicable NFPA Standards. All plan review comments are subject to final on-site field inspections, and testing by the CSFD. Review and approval by the CSFD shall not relieve the applicant of the responsibility of compliance with the International Fire Code. (105.4.4)


 

Contact Us: Email Us - Call: 385-CITY (719-385-2489) - RSS - Privacy, Linking and ADA Policies - designed, developed by projecta.com