NOTE - THE NOTED DISAPPROVED ITEMS MAY NOT CONSTITUTE A COMPLETE LIST OF VIOLATIONS. THE DESIGNER IS TO CONDUCT A COMPLETE RE-REVIEW OF THE PLANS FOR ADDITIONAL VIOLATIONS OF THE STANDARD COMMENTS AND INCORRECT INFORMATION PRIOR TO RESUBMITTING.

 System plans must be picked up within 30 days. All system plans left longer than 30 days will be discarded as abandoned.

VERIZON WIRELESS DATA CENTER
04323 ARROWSWEST DR

Review DateStatusComment(s)
3/4/2013 FYI*****(STANDARD COMMENT 1) This project is: Verizon Data Center, 4323 Arrowswest Dr: interior remodel - expansion of the servers Date of Plans: 2.27.13
FYI(STANDARD COMMENT 3) HEAD EXTENDERS: BE ADVISED: Head Extenders are not allowed in the City of Colorado Springs.
FYI*****(STANDARD COMMENT) REVISION: Revision Sequence: 1 Scope of Revision: DETAILED DEMO PLANS, HYDRAULICS FOR AFFECTED SYSTEMS Date of Revision: 2.27.13 NOTE: Seismic bracing is not part of our review.
FYI*****(STANDARD COMMENT 10) WATER SUPPLY/SYSTEM DEMAND INFORMATION: The Water Flow Calculation show a water supply of having a -78---- PSI Static; 20 PSI Residual; --2600--- GPM Flow. PREACTION ZONE 3 System Demand of --740--- gpm, including --250-- hose demand, at ---63-- psi is needed at the CITY GAGE. All hydraulic designed systems are to have the Hydraulic Placard information sign secured to the sprinkler riser.
1/8/2013 FYI*****(STANDARD COMMENT 1) This project is: Verizon Data Center, 4323 Arrowswest Dr: interior remodel - expansion of the servers Date of Plans: 1.2.12
FYI*****(STANDARD COMMENT 6) The fire sprinkler system is being installed by: WSFP This plan review is based on the requirements found within the adopted International Building Code, International Fire Code, and the 2010 editions of NFPA Standard 13, 13R or 13D as applicable. CSFD does not allow any combustibles into a building until a sprinkler system has passed it's final acceptance test performed by CSFD Inspector's.
FYI*****(STANDARD COMMENT 8) SCOPE OF WORK: Area/scope of work is --DEMO PREACTION SYSTEMS WITHIN ROOMS 143, 144 AND 145 ON 1ST FLOOR; MECH ROMS 2ND FLOOR----of the building. THESE AREA WILL BE PROVIDED WITH CLEAN AGENT SYSTEM.
FYI(STANDARD COMMENT 20) LICENSED INSTALLER: An On-Site Installer shall supervise all on-site work on any fire sprinkler project. This On-Site Installer shall have a current Installer Card issued by RBD, on his person, while on the job site.
FYI(STANDARD COMMENT 35) CERTIFICATE OF INSTALLATION: It is the installer's responsibility to certify through this form (attached to the plans) that the system has been properly installed and tested. The form is to be filled out in its entirety PRIOR TO THE ARRIVAL OF THE FIRE INSPECTOR conducting the final inspection and/or acceptance test of the system. FINAL INSPECTIONS WILL NOT BE CONDUCTED WITHOUT THIS FORM BEING COMPLETED.
FYI(STANDARD COMMENT 36) GENERAL INFORMATION SIGN A general information sign used to identify the system design basis and information relative to the requirements of NFPA 25, shall be provided with a permanently marked weather-proof metal or rigid plastic sign, secured at each system control riser, antifreeze loop and auxiliary control valve. (NFPA 13:24.6)
FYI(STANDARD COMMENT 10) INSPECTIONS Due to the dynamic nature of inspectors schedules, PLEASE call your inspection requests in with ample time to allow scheduling. When calling, please have your complete CSFD plan review number(s) ready for each inspection request. ( i.e. 20001234 - HM -2 or 20000012 - CN - 1) The CSFD Approved sets of plans are to be on site for all inspections.
Attention(STANDARD COMMENT) JAH - SCHEUDLING INSPECTIONS: Your assigned inspector is Jeff Hanenberg. Please call 719-385-5982 and choose option 2 to schedule all construction related inspection activities.
FYI(STANDARD COMMENT 39) PLAN REVIEW/PERMIT FEES: All fire department fees are to be paid prior to issuance of any permits. These fees must be paid directly to the Colorado Springs Fire Department - Development Review Enterprise - at 2880 International Circle - Suite 200-7.
FYI(STANDARD COMMENT) REVIEWS: Colorado Springs Fire Department construction reviews are based upon information provided on the drawings and/or the attached reference material. Issues or features that are not presented within the construction documents are assumed to be complaint with applicable codes/standards. It is the responsibility of the building owner to ensure that minimum code requirement are met as established by the Authority Having Jurisdiction, whether of not the requirements are specifically indicated on the submitted construction documents. The CSFD has reviewed the submittal in accordance with the fire code requirements of the 2003 International Fire Code, CSFD local amendments, City Code Standards, and applicable NFPA Standards. All plan review comments are subject to final on-site field inspections, and testing by the CSFD. Review and approval by the CSFD shall not relieve the applicant of the responsibility of compliance with the International Fire Code. (105.4.4)


 