NOTE - THE NOTED DISAPPROVED ITEMS MAY NOT CONSTITUTE A COMPLETE LIST OF VIOLATIONS. THE DESIGNER IS TO CONDUCT A COMPLETE RE-REVIEW OF THE PLANS FOR ADDITIONAL VIOLATIONS OF THE STANDARD COMMENTS AND INCORRECT INFORMATION PRIOR TO RESUBMITTING.

 System plans must be picked up within 30 days. All system plans left longer than 30 days will be discarded as abandoned.

BASS PRO SHOPS
13012 BASS PRO DR

Review DateStatusComment(s)
2/1/2013 FYI*****(STANDARD COMMENT) This project is: Bass Pro Shops, 13012 Bass Pro Drive: new outdoor store Date of Plans: 11.20.12 You can access our web site for the latest fire department plan review comments: 1. From www.pprbd.org, select PLAN REVIEW then FIND PLANS next COLORADO SPRINGS 2. Scroll down to the correct address. You may then select APPROVED/DISAPPROVED to view comments associated with that particular project.
Disapproved*****(STANDARD COMMENT 19) DISAPPROVED COMMENTS The following information and/or corrections are needed prior to completing a full plan review. Please respond, in writing on letterhead, to each of the following comments: Two of the 4 previous disapproval comments have not been addressed. 1. No code study attached to plans. 4. High-pile Storage information shall be provided see supporting comment below Also review the disapproved plans for additional written comments prior to submittal of new plans.
Disapproved(STANDARD COMMENT) HIGH PILE STORAGE Based upon a review of the construction plans, it has been determined that this facility is capable of storing high-pile stock. If you are NOT planning on storing ordinary combustibles over 12-feet (or over 6-ft for high-hazard combustibles) then the owners must complete the NO STACKING AGREEMENT and attach it to the construction plans prior to submitting the plans for a fire department re-review. However, if you ARE planning on storing combustibles over the allowable limits, you will need to attach the "CSFD High-Pile Questionnaire" to the plans. All forms and packets are available at http://www.springsgov.com/Page.aspx?NavID=1094
Disapproved(STANDARD COMMENT) FIRE PROTECTION SYSTEMS Please indicate what fire protection systems, if any, this structure will be provided with. This must appear on your plan with the code summary of the structure.
FYI(STANDARD COMMENT) CORRECTIONS All corrections and comments are to be submitted back to CSFD in writing, or provid submittal sheets/drawings, etc as requested, to complete the review. Corrections are not accepted over the phone, via fax or verbally.
Attention(STANDARD COMMENT) THE DISAPPROVED ITEMS MAY NOT CONSITITUE A COMPLETE LIST OF VIOLATIONS. IT IS THE RESPONSIBILITY OF THE DESIGNER/ARCHITECT TO CONDUCT A COMPLETE RE-REVIEW OF THE PLANS FOR ADDITIONAL VIOLATIONS OF THE ADOPTED CODES/STANDARDS AND INCORRECT INFORMATION PRIO TO RESUBMITTING.
FYI(STANDARD COMMENT) RESUBMITTALS Re-reviews may be submitted back to the CSFD by direct submittal at the Construction Services counter, or through the Regional Building Department's routing system.
FYI(STANDARD COMMENT) REVIEWS Colorado Springs Fire Department construction reviews are based upon information provided on the drawings and/or the attached reference material. Issues or features that are not presented within the construction documents are assumed to be complaint with applicable codes/standards. It is the responsibility of the building owner to ensure that minimum code requirements are met as established by the Authority Having Jurisdiction, whether or not the requirements are specifically indicated on the submitted construction documents. The CSFD has reviewed the submittal in accordance with the adopted fire code requirements, CSFD local amendments, City Code Standards, and applicable NFPA Standards. All plan review comments are subject to final on-site field inspections, and testing by the CSFD. Review and approval by the CSFD shall not relieve the applicant of the responsibility of compliance with the International Fire Code. (105.4.4)
11/30/2012 FYI*****(STANDARD COMMENT) This project is: Bass Pro Shops, 13012 Bass Pro Drive: new outdoor store Date of Plans: 11.20.12 You can access our web site for the latest fire department plan review comments: 1. From www.pprbd.org, select PLAN REVIEW then FIND PLANS next COLORADO SPRINGS 2. Scroll down to the correct address. You may then select APPROVED/DISAPPROVED to view comments associated with that particular project.
Disapproved*****(STANDARD COMMENT 19) DISAPPROVED COMMENTS The following information and/or corrections are needed prior to completing a full plan review. Please respond, in writing on letterhead, to each of the following comments: 1. No code study attached to plans. 2. Hazmat Triage form and Carbon Dioxide declarations shall be filled out. see supporting comment below 3. Hazmat inventory shall be provided. see supporting comment below 4. High-pile Storage information shall be provided see supporting comment below Also review the disapproved plans for additional written comments prior to submittal of new plans.
Disapproved(STANDARD COMMENT) HIGH PILE STORAGE Based upon a review of the construction plans, it has been determined that this facility is capable of storing high-pile stock. If you are NOT planning on storing ordinary combustibles over 12-feet (or over 6-ft for high-hazard combustibles) then the owners must complete the NO STACKING AGREEMENT and attach it to the construction plans prior to submitting the plans for a fire department re-review. However, if you ARE planning on storing combustibles over the allowable limits, you will need to attach the "CSFD High-Pile Questionnaire" to the plans. All forms and packets are available at http://www.springsgov.com/Page.aspx?NavID=1094
Disapproved(STANDARD COMMENT) HAZARDOUS MATERIALS: Provide an inventory list, including their uses and amounts, for all chemicals and/or compressed gases, stored, handled and/or dispensed on site. Provide listed information on the haz-mat permit amount certification form for all Use/Dispensing/Storage of Hazardous Materials and Flammable Liquids that will be used within this facility. PLEASE INSURE YOU ANSWER ALL QUESTIONS AT THE BOTTOM OF THE FORMS, AND FILL OUT THE REQUESTED INFORMATION. All forms and packets are available at http://www.springsgov.com/Page.aspx?NavID=1094.
Disapproved(STANDARD COMMENT) CARBON DIOXIDE It appears that carbon dioxide will be used in this facility. Prior to approval of these plans we will need a CSFD CO2 declaration completed, signed, dated, and returned with construction set of plans. You fill find this enclosed or you can access it on our website. http://www.springsgov.com/page.aspx?navid=1094
Disapproved(STANDARD COMMENT) FIRE PROTECTION SYSTEMS Please indicate what fire protection systems, if any, this structure will be provided with. This must appear on your plan with the code summary of the structure.
FYI(STANDARD COMMENT) CORRECTIONS All corrections and comments are to be submitted back to CSFD in writing, or provid submittal sheets/drawings, etc as requested, to complete the review. Corrections are not accepted over the phone, via fax or verbally.
Attention(STANDARD COMMENT) THE DISAPPROVED ITEMS MAY NOT CONSITITUE A COMPLETE LIST OF VIOLATIONS. IT IS THE RESPONSIBILITY OF THE DESIGNER/ARCHITECT TO CONDUCT A COMPLETE RE-REVIEW OF THE PLANS FOR ADDITIONAL VIOLATIONS OF THE ADOPTED CODES/STANDARDS AND INCORRECT INFORMATION PRIO TO RESUBMITTING.
FYI(STANDARD COMMENT) RESUBMITTALS Re-reviews may be submitted back to the CSFD by direct submittal at the Construction Services counter, or through the Regional Building Department's routing system.
FYI(STANDARD COMMENT) REVIEWS Colorado Springs Fire Department construction reviews are based upon information provided on the drawings and/or the attached reference material. Issues or features that are not presented within the construction documents are assumed to be complaint with applicable codes/standards. It is the responsibility of the building owner to ensure that minimum code requirements are met as established by the Authority Having Jurisdiction, whether or not the requirements are specifically indicated on the submitted construction documents. The CSFD has reviewed the submittal in accordance with the adopted fire code requirements, CSFD local amendments, City Code Standards, and applicable NFPA Standards. All plan review comments are subject to final on-site field inspections, and testing by the CSFD. Review and approval by the CSFD shall not relieve the applicant of the responsibility of compliance with the International Fire Code. (105.4.4)


 