CSFD FIRE STATION 21
07320 DUBLIN BL

Review DateStatusComment(s)
1/4/2013 FYI*****(STANDARD COMMENT) This project is: CSFD Fire Station 21, 7320 Dublin Bl: new fire station UPGRADE TO FINISH Date of Plans: 11.13.12 You can access our web site for the latest fire department plan review comments: 1. From www.pprbd.org, select PLAN REVIEW then FIND PLANS next COLORADO SPRINGS 2. Scroll down to the correct address. You may then select APPROVED/DISAPPROVED to view comments associated with that particular project.
Attention*****(STANDARD COMMENT) RED-LINED COMMENTS The following RED-LINED items are to be corrected prior to final inspection: 1. FDC shall be located at noted on plumbing sheet, on the back of the building, to prevent conflict with the gas meter.
Attention(STANDARD COMMENT) CONSTRUCTION SPLICES You are strongly encouraged to have any splices that may occur during this project, reviewed by CSFD. Failure to do so, can result in coordination issues that could prevent a final inspection from being completed, thus delaying the issuance of a Certificate of Occupancy.
FYI(STANDARD COMMENT) ACCESS FOR FIREFIGHTING Approved vehicle access for firefighing shall be provided to all construction/demolition sites. Vehicle access shall be either temporary or permanent roads, capable of supporting vehicle loading under all weather conditions. Vehicle access shall be maintained until permanent fire apparatus access roads are available. (2009 IFC 1410)
FYI(STANDARD COMMENT) CONTACTS FOR FLOW TESTING HYDRANTS PUBLIC/CITY OWNED HYDRANTS: Contact SEAN HIGBEE, CSU at 668-4595 or via email at shigbee@csu.org to schedule an ACTUAL flow test. Be sure to provide them with a CSFD plan review number to include with their flow reports. CSFD need not be present when City Utilities flow tests hydrants as we will accept their reports. PLEASE ALLOW 1-2 WEEKS NOTICE PRIVATE HYDRANTS: Contact your assigned inspector to schedule a flow test of PRIVATE OWNED hydrants. A contractor capable of performing the test will be required as CSFD Inspectors WITNESS only. CSFD will not accept flow test results we have not witnessed.
FYI(STANDARD COMMENT) FIRE EXTINGUISHERS Fire Extinguishers shall be provided in accordance with Section 906 of the 2009 IFC. Install extinguishers in highly visible and accessible locations, never in a dead-end area, and always try to place them near an exit pathway or at an exit(s). Mount 4" off floor to a maximum of 5 ft. to the top of the fire ext. (HINT: About waist high is perfect.) "FIRE EXTINGUISHER" signs may need to be posted to properly identify where the units are located if they're not highly visible.
Attention(STANDARD COMMENT) FIRE EXTINGUISHERS PLAN REVIEWS DO NOT INCLUDE REVIEW OF TYPE, SIZE OR PLACEMENT OF FIRE EXTINGUISHERS.
FYI(STANDARD COMMENT) ADDRESSING Address shall be posted on street addressed side of structure. Minimum 5" numbers with 1/2" stroke. Contrasting color to background. (2009 IFC 505.1)
FYI*****(STANDARD COMMENT) KNOX (TM) ENTRY FOR NEW BUILDINGS KNOX (TM) --XXX----Box It is recommended that all KNOX (TM) boxes be placed in a highly accessible location approximately 10 feet off of the ground, and usually placed near the front entrance to the building. KNOX (TM) Security Equipment is the only approved type, and must be ordered directly through the CSFD Division of the Fire Marshal at 2880 International Circle, Suite 200-7, or by calling (719) 385-5982. ***************ALLOW AT LEAST 4 WEEKS DELIVERY TIME ************************* YOUR FINAL WILL NOT BE APPROVED WITHOUT THE KNOX SECURITY EQUIPMENT INSTALLED! YOU MUST ALSO CONTACT OUR OFFICE AT LEAST 1 WEEK PRIOR TO YOUR REQUEST FOR FIRE FINALS TO ARRANGE FOR A CSFD FIRE INSPECTOR TO MEET YOU AT THE SITE TO INSTALL PROPER KEYS FOR THE BUILDING INTO THE KNOX SECURITY UNIT.
FYI*****(STANDARD COMMENT) HAZ-MAT CERTIFICATION FORM The hazardous materials amount certification form has been completed, submitted and attached to the building plans. This form states that there WILL NOT be excessive amounts of hazardous materials at this facility. CSFD Inspectors will verify this when the Fire final inspections of the occupancy are conducted.
FYI(STANDARD COMMENT) NATURAL GAS FUELED GENERATORS Where the gas supply is connected to the building gas supply system, it shall be connected on the supply side of the main gas shutoff valve and marked as supplying an emergency generator. The building's main gas shutoff valve shall be marked or tagged to indicate The existence of the separate EPS shutoff valve. Valving for natural gas-fueled prime movers should be configured so that the gas supply to the prime mover cannot be inadvertently or intentionally shut off by anyone other than qualified personnel such as the gas supplier. If valves are placed in an isolated area, a secure area or locking the valve open is recommended. 2005 NFPA 110
FYI*****(STANDARD COMMENT) FIRE PROTECTION SYSTEMS The following systems are present or required in this facility: ---XXX--Fire Alarm System ---XXX--Water-Based Suppression System (fire sprinklers, standpipes, etc) Applicable Fire Protection System plans shall be submitted to the CSFD Construction Services office in the Regional Development Center.
FYI(STANDARD COMMENT 10) INSPECTIONS Due to the dynamic nature of inspectors schedules, PLEASE call your inspection requests in with ample time to allow scheduling. When calling, please have your complete CSFD plan review number(s) ready for each inspection request. ( i.e. 20001234 - HM -2 or 20000012 - CN - 1) The CSFD Approved sets of plans are to be on site for all inspections.
FYI(STANDARD COMMENT) SCHEDULING INSPECTIONS: Please call 719-385-5982 Extension 2 to schedule all construction related inspection activities.
FYI(STANDARD COMMENT) REVIEWS Colorado Springs Fire Department construction reviews are based upon information provided on the drawings and/or the attached reference material. Issues or features that are not presented within the construction documents are assumed to be complaint with applicable codes/standards. It is the responsibility of the building owner to ensure that minimum code requirements are met as established by the Authority Having Jurisdiction, whether or not the requirements are specifically indicated on the submitted construction documents. The CSFD has reviewed the submittal in accordance with the adopted fire code requirements, CSFD local amendments, City Code Standards, and applicable NFPA Standards. All plan review comments are subject to final on-site field inspections, and testing by the CSFD. Review and approval by the CSFD shall not relieve the applicant of the responsibility of compliance with the International Fire Code. (105.4.4)
FYI(STANDARD COMMENT) PERMITS Insure all applicable permits are obtained from the Regional Building Department and the Colorado Springs Fire Department for the work that is being done at this site.
1/4/2013 FYI*****(STANDARD COMMENT) HAZ-MAT TRIAGE FORM The hazardous materials amount certification form has been completed, submitted and attached to the building plans. This form states that there WILL NOT be excessive amounts of hazardous materials at this facility. CSFD Inspectors will verify this when the Fire final inspections of the occupancy are conducted. Natural Gas Generator indicated Personal size oxygen tanks for medical emergencies (on vehicles) UPS only to run station computers, not large enough to cause concern.
12/19/2012 IRoom Design Method - Light Hazard - Dayroom Doors shall be automatic or self-closing Walls shall have minimum rating of 30-minutes.
12/6/2012 FYI*****(STANDARD COMMENT) This project is: CSFD Fire Station 21, 7320 Dublin Bl: new fire station UPGRADE TO FINISH Date of Plans: 11.13.12 You can access our web site for the latest fire department plan review comments: 1. From www.pprbd.org, select PLAN REVIEW then FIND PLANS next COLORADO SPRINGS 2. Scroll down to the correct address. You may then select APPROVED/DISAPPROVED to view comments associated with that particular project.
Disapproved*****(STANDARD COMMENT 19) DISAPPROVED COMMENTS The following information and/or corrections are needed prior to completing a full plan review. Please respond, in writing on letterhead, to each of the following comments: 1. Plans indicate the use of a generator - what type of fuel does this generator run on? See additional comments regarding hazardous materials and the Triage Form that still needs to be filled out. 2. Relocate the FDC to the building as noted Also review the disapproved plans for additional written comments prior to submittal of new plans.
Disapproved(STANDARD COMMENT) HAZARDOUS MATERIALS: Provide an inventory list, including their uses and amounts, for all chemicals and/or compressed gases, stored, handled and/or dispensed on site. Provide listed information on the haz-mat permit amount certification form for all Use/Dispensing/Storage of Hazardous Materials and Flammable Liquids that will be used within this facility. PLEASE INSURE YOU ANSWER ALL QUESTIONS AT THE BOTTOM OF THE FORMS, AND FILL OUT THE REQUESTED INFORMATION. All forms and packets are available at http://www.springsgov.com/Page.aspx?NavID=1094.
FYI(STANDARD COMMENT) CORRECTIONS All corrections and comments are to be submitted back to CSFD in writing, or provid submittal sheets/drawings, etc as requested, to complete the review. Corrections are not accepted over the phone, via fax or verbally.
Attention(STANDARD COMMENT) THE DISAPPROVED ITEMS MAY NOT CONSITITUE A COMPLETE LIST OF VIOLATIONS. IT IS THE RESPONSIBILITY OF THE DESIGNER/ARCHITECT TO CONDUCT A COMPLETE RE-REVIEW OF THE PLANS FOR ADDITIONAL VIOLATIONS OF THE ADOPTED CODES/STANDARDS AND INCORRECT INFORMATION PRIO TO RESUBMITTING.
FYI(STANDARD COMMENT) RESUBMITTALS Re-reviews may be submitted back to the CSFD by direct submittal at the Construction Services counter, or through the Regional Building Department's routing system.
FYI(STANDARD COMMENT) REVIEWS Colorado Springs Fire Department construction reviews are based upon information provided on the drawings and/or the attached reference material. Issues or features that are not presented within the construction documents are assumed to be complaint with applicable codes/standards. It is the responsibility of the building owner to ensure that minimum code requirements are met as established by the Authority Having Jurisdiction, whether or not the requirements are specifically indicated on the submitted construction documents. The CSFD has reviewed the submittal in accordance with the adopted fire code requirements, CSFD local amendments, City Code Standards, and applicable NFPA Standards. All plan review comments are subject to final on-site field inspections, and testing by the CSFD. Review and approval by the CSFD shall not relieve the applicant of the responsibility of compliance with the International Fire Code. (105.4.4)
4/18/2012 FYIThis is a courtesy review at the request of Kenny Rankin - CSFD. The plans reviewed have "As Resubmitted 4/4/12" written in pencil on the top-right of the first page. The construction plans are currently disapproved. Please see the previous disapproval comments. Each of these comments will need to be addressed in writing at the next submittal. The information on the civil/utility plans looked acceptable in terms of fire hydrant location and flow. On sheet C-2, there is indication of the fire department connection (FDC) as part of the fire sprinkler supply line. I would suggest a wall mount FDC. Also, there must be an exterior water-flow indicator (horn/strobe) located within 20 feet of the FDC. I was not able to find any indication of an exterior water-flow indicator on any sheet of the preliminary plans.
FYICourtesy review continued... Fire Protection Comments - this is a preliminary report based only on the information provided in the special systems sheets (E1.5 & E1.6) A full submittal for both the fire alarm and fire sprinkler system will be required by a license fire protection contractor. The submittal must include full design drawings, calculations, and product information sheets. A pull station needs to be added by the left, rear apparatus bay man door. The environment of the SCBA room, Geo pump room, and storage rooms 202 & 223 may not be an appropriate environment for smoke detectors if the will be dusty or humid. Confirm the environment won't subject smoke detectors to false activations. The smoke detectors in the upper hall outside the bunks room need to be installed as close tot he bunk rooms as possible to prevent false alarms due to steam from the bathrooms. A smoke detector needs to be added in the two bunk room, in the officer room. In addition, add audible notification in officer rooms 215 or 216 to meet minimum sound level values. The location of the fire alarm control panel is not shown. This either needs to be located at the main entrance to the fire stations, or have a full function remote annunciator located at the main entrance.
1/20/2012 FYI*****(STANDARD COMMENT 1) This project is: Colorado Springs Fire Department Station 21 6042 Peterson Rd New Fire Station Date of Plans: 01/03/12 You can access our web site for the latest fire department plan review comments: 1. From www.pprbd.org, select PLAN REVIEW then FIND PLANS next COLORADO SPRINGS 2. Scroll down to the correct address. You may then select APPROVED/DISAPPROVED to view comments associated with that particular project.
Disapproved*****(STANDARD COMMENT 19) DISAPPROVED COMMENTS The following information and/or corrections are needed prior to completing a full plan review. Please respond, in writing on letterhead, to each of the following comments: 1. Will there be an emergency generator on this site? Also review the disapproved plans for additional written comments prior to submittal of new plans.
Disapproved(STANDARD COMMENT) DEVELOPMENT PLAN Attach copies of the "City Approved" development plan to each set of construction plans submitted to the Colorado Springs Fire Department for review.
Disapproved(STANDARD COMMENT) WATER PLANS The City APPROVED" fire hydrant and water main plans are to be ATTACHED to all sets of construction plans for CSFD plan reviews.
Disapproved(DISAPPROVED) FIRE FLOW REPORT Provide confirmation on the fire flow results from Colorado Springs Utilities. A copy of their report for this area is required to be provided with your plan submittals. When multiple fire flows are provided from CSU, please indicate all flows on your submitted plans. NOTE - To request a fire flow report, please go to: http://www.csu.org/business/businesswithus/documents/item10501.pdf
Disapproved(STANDARD COMMENT) TEMPORARY ADDRESS A temporary address has been assigned to these plans. CSFD will not approve the construction plans until the Regional Building Department Enumerations Office has assigned a permanent address to this facility, and has approved the construction plans.


 