| Review Date | Status | Comment(s) |
| 10/30/2009 |
FYI | *****(STANDARD COMMENT 1) This project is: Palisades @ Broadmoor: 4542 Palisades Park Vw: Retrofit PRV to existing riser
ATTENTION: See our web site for our latest plan review comments for your job at:
www.springsgov.com - go to "City Agencies" (tab on the teal bar to get a drop box) - click on - "Fire Department" - (Using the links down the left side of the page), click on - "Web Guide." Once you're into the Web Guide, click on "Plan Review Status" This will also give you access to numerous other items that may assist you in your future project design work.
|
| FYI | *****(STANDARD COMMENT 6) The fire sprinkler system is being installed by: FIRE SYSTEMS WEST
This plan review is based on the requirements found within the 2003 Editions of the International Building Code, International Fire Code, and the 2007 editions of NFPA Standard 13, 13R or 13D as applicable.
CSFD does not allow any combustibles into a building until a sprinkler system has passed it's final acceptance test performed by CSFD Inspector's. |
| FYI | *****(STANDARD COMMENT 8) SCOPE OF WORK:
Area/scope of work is --PRV RETROFIT--------of the building.
|
| FYI | *****(STANDARD COMMENT 10) WATER SUPPLY/SYSTEM DEMAND INFORMATION:
The Water Flow Calculation show a water supply of having a 165- Static;
New Calculations were not required since the original system was designed with a static of 158 psi. |
| FYI | (13) ELECTRICAL SUPERVISION REQUIRED:
The required electrical supervision of all control valves and water-flow switches of this automatic fire sprinkler system is to be provided. An approved central station, remote station or proprietary supervising station as defined by national standards shall monitor this supervision.
PLEASE NOTE - Separate Fire Department approved plans and permits are to be obtained prior to the installation of the required sprinkler system monitoring.
A Knox Box is also required. Contact the CSFD for the information needed to order this key box. |
| FYI | (STANDARD COMMENT 20) LICENSED INSTALLER: An On-Site Installer shall supervise all on-site work on any fire sprinkler project. This On-Site Installer shall have a current Installer Certificate, on his person, while on the job site.
|
| FYI | *****(STANDARD COMMENT 21) PRESSURE-REDUCING DEVICE: The system pressure is over 175 psi therefore a pressure-reducing device and a pressure relief device is required by NFPA 13: 8.16.1.2.
Insure the relating pressure gages and valves required by this section are also provided.
PRV WILL BE SET TO 165 PSI |
| FYI | (STANDARD COMMENT 35) CERTIFICATE OF INSTALLATION: Attached to the approved plans is a "Certificate of Installation".
It is the installer's responsibility to certify through this form that the system has been properly installed and tested.
The form is to be filled out in its entirety PRIOR TO THE ARRIVAL OF THE FIRE INSPECTOR conducting the final inspection and/or acceptance test of the system.
FINAL INSPECTIONS WILL NOT BE CONDUCTED WITHOUT THIS FORM BEING COMPLETED.
|
| FYI | (STANDARD COMMENT 36) INSPECTIONS
Minimum 2-business days notice is required to schedule an inspection. Please have your eight digit "Fire Department Plan Review Number" ready when calling to schedule an inspection. |
| FYI | (STANDARD COMMENT) KHJ - SCHEUDLING INSPECTIONS:
STATIONS 1, 2, 3, 4, 5, 9, 13, 16:
Starting October 3, 2005, Fire Inspectors will be scheduling their own calendars. Your assigned Inspector is Kris Johnson. You may contact him at 719-385-7257 to schedule all construction related inspection activities
|
| FYI | (STANDARD COMMENT 39) ATTENTION: CSFD FEES. All fire department fees are to be paid prior to issuance of any permits. These fees must be paid directly to the Colorado Springs Fire Department - Development Review Enterprise - at 2880 International Circle - Suite 200-7. The Regional Building Department will NOT issue a building permit with out proof the fire department fees have been paid. |