Back to City Engineering
line

Stormwater Projects
line
*Camp Creek
line
*1st Community Meeting - October 22, 2013
line
*2nd Community Meeting - December 12, 2013
line
*3rd Community Meeting - February 25, 2014
line
*4th Community Meeting - April 29, 2014
line
*Cottonwood Creek Stabilization - La Madrina
line
*Cottonwood Creek Stabilization - PDM
line
*Greencrest Channel
line
*Mirage Channel Reconstruction
line
*North & South Douglas Creek
line
*Sand Creek Ponds
line
Permits, Applications and Fees
line
Reference Materials
line

Frequently Asked Questions
line

PO Box 1575, Mail Code 410
30 S. Nevada Ave, Suite 401
Colorado Springs, CO 80903
Phone: (719) 385-5918
Fax: (719) 385-5537
Email: cityengineering@sp. . .





City of Colorado Springs / City Engineering / Stormwater Projects / Camp Creek

Camp Creek

Current Status: Wilson and Company began work on the Camp Creek project September 2013.  They held their third open house on February 25, 2014. The project team is currently developing the proposed plan.

Background: Camp Creek flows southward from the Navigators campus through Garden of the Gods Park and along 31stStreet in the Pleasant Valley neighborhood. Since the Waldo Canyon Fire, rainfall events have produced greater amounts of sediment and debris loads and have increased stormwater runoff in Camp Creek.  These factors make the already aging and deteriorating channel along 31stStreet even more susceptible to flooding and damage.

The city has selected the consulting firm Wilson and Company to lead community meetings and perform analysis on the drainage basin to develop alternatives and a preferred course of action for construction of flood mitigation structures/facilities.   

Project Progress:

May 19, 2014 - Project Newsletter May 2014

Apr 29, 2014 - Fourth Community Meeting: Presentation of Proposed Plan and Public Response 

Mar 10, 2014 - Project Newsletter March 2014

Feb 25, 2014 - Third Community Meeting: Presentation of Alternatives and Public Response

Jan 14, 2014 - Project Newsletter January 2014

Dec 12, 2013 - Second Community Meeting: Handouts and Public Response

Nov 7, 2013 - Project Newsletter November 2013

Oct 31, 2013 - Project Progress

Oct 22, 2013 - Initial Community Meeting: Handouts and Public Response

Sep 24, 2013 - Project Newsletter October 2013

Sep 6, 2013 – Press Release - City Stormwater Update

Project Contacts:

Mike Chaves (Project Manager, 385-5408)